Permit Details

Permit Search

Permit

Storage Building

229 SW MARVIN BURNETT RD
LAKE CITY, FL 32025

Permit #
000054016
Application #
72691
Status Completed
  1. Submitted Aug 13, 2025
  2. Issued Sep 9, 2025
  3. Expires Aug 22, 2026
  4. Completed Feb 23, 2026

Property

Parcel #
08158-002
Owner
Barger Charles John Ii Aka Charles J Bargar, Bargar Chun C
Acres
6.64
Subdivision
—
Zoning
RSF-2
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Accessory Use
Finished floor requirement
Non-Habitable Structure
Fema map number
12023C0292D
Type of Structure
Storage Building
Commercial or Residential?
Residential
Total Area (Sqft)
1680
Septic# (00-0000) or (X00-000)
25-0651
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setback Rear
10' (ACCESSORY)
Building Code Construction Type
III
Building Code Element
B
Building Code Occupancy Types
Storage
Occupancy Use Title
NON-HABITABLE STRUCTURE
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Building Height
12
Building Length
56'
Building Width
30'
Service Amps
0
Slab
New
Mechanical
No
Electrical
No
Plumbing
No

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified.
  3. Point Review - Documents Required
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Ready for applicant submittal
  6. Application submitted by applicant.
  7. City of Lake City Utilities Notified.
  8. Application submitted by applicant.
  9. Point Review - Reviewed
  10. Zoning Review - Reviewed
  11. Plan Review - Building Approved
  12. Plan Review - Reviewed
  13. Final Review - Processing
  14. Final Review - Reviewed
  15. Final Review - Payment Needed
  16. Permit Issued
  17. Final Review - Complete

Contractors

This is an owner-builder project.

Inspections

  1. Aug 21, 2025

    Septic Release Inspection

    Inspected by Health Dept

  2. Sep 24, 2025

    Passed: Building - Monolithic Slab

    Mono Slab With 2 # 5 Rebar On Chairs And Electric Bond,

    Inspected by Gary Pitzer

  3. Feb 23, 2026

    Passed: Building - Final

    Building Completed

    Inspected by Gary Pitzer