Roof Replacement or Repair
Permit
| Application #: | 72104 |
| Permit #: |
000053771 |
| Related Permit: |
|
| Submitted: | Wednesday, July 16, 2025 |
| Issued: | Tuesday, August 5, 2025 |
| Expires: | Monday, August 25, 2025 |
| Completed: | Monday, August 25, 2025 |
| Status: |
Completed |
| Septic Release? |
N/A |
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0289D |
| Type Roofing Job |
Overlay with Metal |
| Further Job Details (Explain if decking is being replaced and or Repairs are being done.) |
Supply and install 1"x4" wood purlins and overlay with metal |
| Type of structure |
Mobile Home |
| Commercial or Residential |
Residential |
| Roof Area (for this job) Sq Ft |
1000 |
| No. of Stories |
0 |
| Roof Pitch |
2:12 to 4:12 |
| Is the existing roof being removed? |
No |
| Explain if not removing the existing roofing material? |
Supply and install 1"x4" wood purlins and overlay with metal |
| Type of New Roofing Product |
Metal |
| Florida Product Approval Number |
FL13768-R5 |
| Product Manufacturer |
Agrimetal |
| Product Description |
Metal |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Sealed roof decking options: (Must select an option.) |
Other (explain) |
| Sealed roof decking explanation for other option. |
Supply and install 1"x4" wood purlins and overlay with metal |
| Ventilation: |
Off-ridge Vent |
| Flashing: |
Replace All |
| Drip Edge: |
Replace All |
| Valley Treatment: |
New Metal |
| Any cable and/or race-way wiring located on or within the roof assembly? |
No |
Review Notes
| 7/16/2025 |
Application pending. |
| 7/16/2025 |
Application submitted by applicant. |
| 7/16/2025 |
Application submitted by applicant. |
| 7/16/2025 |
Final Review - Corrections Needed |
| 7/18/2025 |
Final Review - Corrections Needed |
| 7/23/2025 |
Final Review - Corrections Needed |
| 7/24/2025 |
Final Review - Corrections Needed |
| 7/29/2025 |
Final Review - Corrections Needed |
| 7/30/2025 |
Final Review - Corrections Needed |
| 7/31/2025 |
Final Review - Corrections Needed |
| 8/1/2025 |
Final Review - Payment Needed |
| 8/5/2025 |
Permit Issued |
| 8/5/2025 |
Final Review - Complete |
Contractors
| Name / Business |
License |
Title |
Role |
Daniel Byrd Byrds Eye Roofing Inc
|
CCC1332899 |
Cert. Roofing |
Contractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Passed: Re-Roof - In Progress |
Metal Over Shingles |
Matt Forsyth |
8/6/2025 |
| Passed: Re-Roof - Roof Pictures Review |
|
Matt Forsyth |
8/7/2025 |
| Passed: Re-Roof - Roof Affidavit Review |
|
Matt Forsyth |
8/7/2025 |
| Cancelled: Re-Roof - In Progress |
|
Neonta Anderson |
8/25/2025 |
| Passed: Re-Roof - Final |
|
Matt Forsyth |
8/25/2025 |
| Cancelled: Re-Roof - Roof Pictures Review |
|
Matt Forsyth |
8/25/2025 |
| Cancelled: Re-Roof - Roof Affidavit Review |
|
Matt Forsyth |
8/25/2025 |