Swimming Pool and Spa
Permit
| Application #: | 71952 |
| Permit #: |
000053728 |
| Related Permit: |
|
| Submitted: | Tuesday, July 8, 2025 |
| Issued: | Thursday, July 31, 2025 |
| Expires: | Wednesday, February 11, 2026 |
| Completed: | Wednesday, February 11, 2026 |
| Status: |
Completed |
| Septic Release? |
Yes |
Job Details
| Elevation regulation |
Accessory Use |
| Finished floor requirement |
Non-Habitable Structure |
| Fema map number |
12023C0280D |
| Is this for residential or commercial use? |
Residential |
| This is the construction of a: |
Both Pool and Spa |
| Setbacks Front |
30' |
| Setback Side 1 |
25' |
| Setbacks Rear |
25' |
| Setback Side 2 |
25' |
| Building Code Edition |
2023 Florida Building Code 8th Edition and 2020 National Electrical Code |
| Septic# (00-0000) or (X00-000) |
25-0556 |
Review Notes
| 7/8/2025 |
Application pending. |
| 7/15/2025 |
Zoning Review - Documents Required |
| 7/15/2025 |
Point Review - Pre-submittal Review Notes |
| 7/15/2025 |
Zoning Review - Documents Required |
| 7/15/2025 |
Zoning Review - Documents Required |
| 7/18/2025 |
Point Review - Ready for applicant submittal |
| 7/24/2025 |
Zoning Review - Documents Required |
| 7/24/2025 |
Application submitted by applicant. |
| 7/29/2025 |
Point Review - Ready for applicant submittal |
| 7/29/2025 |
Point Review - Reviewed |
| 7/29/2025 |
Zoning Review - Reviewed |
| 7/31/2025 |
Plan Review - Plumbing Approved |
| 7/31/2025 |
Plan Review - Electrical Approved |
| 7/31/2025 |
Plan Review - Building Approved |
| 7/31/2025 |
Plan Review - Reviewed |
| 7/31/2025 |
Final Review - Processing |
| 7/31/2025 |
Final Review - Reviewed |
| 7/31/2025 |
Final Review - Payment Needed |
| 7/31/2025 |
Permit Issued |
| 8/1/2025 |
Final Review - Complete |
Contractors
| Name / Business |
License |
Title |
Role |
Yadami Mendoza North Florida Pools & Spas Llc
|
CPC1459321 |
Cert. Residential Pool |
Contractor |
Marcus Matthews Matthews Electric Llc
|
EC13005459 |
Electrical Contractor |
Subcontractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
7/30/2025 |
| Passed: Swimming Pool - Pool Steel and Ground |
|
Matt Forsyth |
8/25/2025 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/25/2025 |
| Passed: Swimming Pool - Pool Deck/Piping Pressure |
|
Matt Forsyth |
9/19/2025 |
| Passed: Electrical - Pool/Deck Bonding |
|
Matt Forsyth |
9/30/2025 |
| Passed: Swimming Pool - Pool Safety and Final |
|
Matt Forsyth |
2/11/2026 |