Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Remodel Permit

Address 278 SE MARINO WAY
HIGH SPRINGS, FL 32643
Parcel #: 09984-002
Acres: 4.05
Owner: Villanueva Zolia, Rodriguez Jose
Subdivision: Oleno Estates
Zoning: A-3
Flood Zone: X
District: 4
Application #: 71017
Permit #: 000053649
Related Permit:
Submitted: Thursday, May 15, 2025
Issued: Wednesday, July 23, 2025
Expires: Monday, January 19, 2026
Completed:
Status: Final Review - Complete
Septic Release? No
Notes:
*REROOF PERMIT SEPERATE-- PERMIT #53342
Job Details
Finished floor requirement
Fema map number 12023C0294D
This is the construction of a SFD/UTILITY
Setbacks Front 25.00
Setback Side 1 10.00
Setback Side 2 10.00
Setbacks Rear 15.00
Stories 1
Heated Area (Sqft) 1396.00
Total Area (Sqft) 1797.00
Building Code Edition Florida Building Code 2014 5th Edition & 2011 National Electrical Code
Review Notes
5/14/2025 Application pending.
5/15/2025 Application submitted by applicant.
5/16/2025 Final Review - Corrections Needed NEEDED * DETAILED SCOPE OF WORK
6/9/2025 Final Review - Corrections Needed NEED *WIGBERTO BAEZ STATE LICENSE & LIABILITY INSURANCE & WORKERS COMP EXPIRED.
6/20/2025 Final Review - Corrections Needed NEEDED: * daniel to register mechanical license CMC057034 *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED
6/21/2025 Final Review - Corrections Needed NEEDED: *DANIEL TO REGISTER MECHANICAL LICENSE CMC057034 *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *if ac to be replaced, must be pulled as seperate permit
6/24/2025 Final Review - Corrections Needed NEEDED: *DANIEL TO REGISTER MECHANICAL LICENSE CMC057034 *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
6/25/2025 Final Review - Corrections Needed NEEDED: *DANIEL TO REGISTER MECHANICAL LICENSE CMC057034 *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/4/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE REVEICE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/7/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE REVEICE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/13/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE REVEICE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/14/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE REVEICE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/15/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE RECEIVE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/18/2025 Final Review - Corrections Needed SPOKE TO OFFICE STAFF ON 7/2 THEY AC WILL BE PULLED UNDER SEPERATE PERMIT - ONCE WE RECEIVE APP FOR AC WE CAN MOVE FORWARD WITH THIS APP NEEDED: *PLAN REVIEWER TO DETERMINE IF ANYTHING FURTHER IS NEEDED *IF AC TO BE REPLACED, MUST BE PULLED AS SEPERATE PERMIT
7/23/2025 Final Review - Payment Needed
7/23/2025 Permit Issued Permit #000053649 created and approved.
7/24/2025 Final Review - Complete
Contractors
Name/ Business License Title Role
Suleyvi Villanueva
Svm Magnolia Construction Llc
Liability Insurance & Workers Comp Expired.
CBC1266742 Cert. Building Contractor
Wigberto Baez
Del Sol Electric Llc
EC13004859 Cert Electical Subcontractor
Daniel S Echt
Decht Mechanical
CFC1428450 Cert. Plumbing Subcontractor
Daniel Decht
Decht Mechanical
CMC057034 Cert. Mechanical Subcontractor
Inspections
Inspection Notes Performed By Date
Documents
File Name Date File Size