| 5/28/2025 |
Application pending. |
| 6/4/2025 |
Point Review - Pre-submittal Review Notes |
| 6/9/2025 |
Point Review - Ready for applicant submittal |
| 6/10/2025 |
Point Review - Ready for applicant submittal |
| 6/11/2025 |
Point Review - Ready for applicant submittal |
| 6/12/2025 |
Point Review - Ready for applicant submittal |
| 6/14/2025 |
Point Review - Ready for applicant submittal |
| 6/15/2025 |
Point Review - Ready for applicant submittal |
| 6/16/2025 |
Point Review - Ready for applicant submittal |
| 6/18/2025 |
Point Review - Ready for applicant submittal |
| 6/19/2025 |
Point Review - Ready for applicant submittal |
| 6/20/2025 |
Point Review - Ready for applicant submittal |
| 6/21/2025 |
Point Review - Ready for applicant submittal |
| 6/22/2025 |
Point Review - Ready for applicant submittal |
| 6/23/2025 |
Point Review - Ready for applicant submittal |
| 6/24/2025 |
Point Review - Ready for applicant submittal |
| 6/25/2025 |
Point Review - Ready for applicant submittal |
| 6/25/2025 |
Application submitted by applicant. |
| 6/25/2025 |
Point Review - Reviewed |
| 6/25/2025 |
Zoning Review - Reviewed |
| 6/26/2025 |
Plan Review - Plumbing Approved |
| 6/26/2025 |
Plan Review - Electrical Approved |
| 6/26/2025 |
Plan Review - Building Approved |
| 6/26/2025 |
Plan Review - Reviewed |
| 6/26/2025 |
Final Review - Processing |
| 6/30/2025 |
Final Review - Reviewed |
| 6/30/2025 |
Final Review - Payment Needed |
| 6/30/2025 |
Permit Issued |
| 6/30/2025 |
Final Review - Complete |
| 7/13/2025 |
Point Review - Reviewed |