| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Reminder Will Need Compaction Test For Slab |
Troy Crews |
7/21/2025 |
| Passed: Building - Monolithic Slab |
|
Troy Crews |
7/31/2025 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/31/2025 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
8/8/2025 |
| Release to power company |
|
Troy Crews |
8/8/2025 |
| Rescheduled 8/15/2025:Building - Ext Strapping/Wall Sheathing |
|
Neonta Anderson |
8/13/2025 |
| Rescheduled 8/15/2025:Building - Roof Decking |
|
Neonta Anderson |
8/13/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
8/15/2025 |
| Passed: Building - Roof Decking |
|
Troy Crews |
8/15/2025 |
| Passed: Building - Framing |
Simpson Sdwc Screws Used For Headers And Truss Tie Down |
Troy Crews |
8/27/2025 |
| Passed: Building - Window Attachment |
All Factory Holes Have A Screw |
Troy Crews |
8/27/2025 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
8/27/2025 |
| Passed: Electrical - 1st Underground Rough–In |
Second Roof In Wall Inspection |
Troy Crews |
8/27/2025 |
| Failed: Plumbing/Gas - 1st Underground Rough–In |
Plumbing Not Complete No Pressure On Water Lines Drain Line For Tub Not Complete |
Troy Crews |
8/28/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Need Nail Guard On Dryer Vent Pipe |
Anthony Aslan |
8/29/2025 |
| Passed: Building - Insulation |
|
Troy Crews |
9/3/2025 |
| Septic Release Inspection |
|
Health Dept |
9/5/2025 |
| Passed: Electrical - Permanent Power |
|
Gary Pitzer |
10/6/2025 |
| Release to power company |
|
Gary Pitzer |
10/6/2025 |
| Failed: Building - Final |
Electric Outlets Are Not Complete In Island Cabinet |
Gary Pitzer |
10/21/2025 |
| Passed: Building - Final |
All Requirements Met To Release Co |
Matt Forsyth |
10/23/2025 |