Permit

Solar Power System

144 SE PATIENCE PL
LAKE CITY, FL 32025

Permit #
000053455
Application #
71508
Status Completed
  1. Submitted Jun 16, 2025
  2. Issued Jun 25, 2025
  3. Expires Dec 28, 2025
  4. Completed Jul 2, 2025

Property

Parcel #
08300-094
Owner
A Moreno Flores Ismael,
Acres
0.36
Subdivision
Woodhaven Unit Iv
Zoning
RSF-2
Flood zone
AH
District
5

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0313D
PV Type
Utility Interactive PV System- (DC to AC with utility connection)
Grounding
N.E.C. Chapter 690
AC Options
USE-2
AC Options (Cont..)
In Conduit;THWN-2
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Power Company
Clay Electric
Residential or Commercial?
Residential
Where are the panels mounted?
Roof Mounted
Service Amps
200

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified.
  3. Point Review - Pre-submittal Review Notes
  4. Point Review - Pre-submittal Review Notes
  5. Point Review - Pre-submittal Review Notes
  6. Point Review - Ready for applicant submittal
  7. Point Review - Ready for applicant submittal
  8. Application submitted by applicant.
  9. City of Lake City Utilities Notified.
  10. Point Review - Printed-Online Application
  11. Point Review - Reviewed
  12. Zoning Review - Reviewed
  13. Plan Review - Electrical Approved
  14. Plan Review - Building Approved
  15. Plan Review - Reviewed
  16. Final Review - Processing
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Final Review - Complete

Contractors

  • Alberto Murias

    Peak Energy Corp

    License
    EC13012590
    Title
    Cert. Electrical
    Role
    Contractor

    County License Expired.

Inspections

  1. Jul 1, 2025

    Passed: Electrical - Permanent Power

    Service Change Passed By Brandon Celli

    Inspected by Private Provider

  2. Jul 1, 2025

    Passed: Solar - Solar Final

    Solar Final Passed By Brandon Celli

    Inspected by Private Provider

  3. Jul 2, 2025

    Release to power company

    Inspected by Private Provider

  4. Jul 2, 2025

    Release to power company

    Inspected by Private Provider