Permit Details

Permit Search

Permit

Solar Power System

223 SW MEADOWLANDS DR
LAKE CITY, FL 32024

Permit #
000053421
Application #
71486
Status Completed
  1. Submitted Jun 16, 2025
  2. Issued Jun 20, 2025
  3. Expires Apr 12, 2026
  4. Completed Oct 14, 2025

Property

Parcel #
09617-227
Owner
Lye Charles, Lye Eileen
Acres
5.01
Subdivision
Meadowlands Phase 2
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0485C
PV Type
Utility Interactive PV System- (DC to AC with utility connection)
Grounding
N.E.C. Chapter 690
AC Options
UF
AC Options (Cont..)
In Conduit;THWN-2
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Power Company
Clay Electric
Residential or Commercial?
Residential
Where are the panels mounted?
Roof Mounted
Service Amps
200

Status & Review History

  1. Application pending.
  2. Point Review - Ready for applicant submittal
  3. Application submitted by applicant.
  4. Point Review - Processing
  5. Point Review - Printed-Online Application
  6. Point Review - Reviewed
  7. Zoning Review - Reviewed
  8. Plan Review - Electrical Approved
  9. Plan Review - Building Approved
  10. Plan Review - Reviewed
  11. Final Review - Processing
  12. Final Review - Payment Needed
  13. Permit Issued
  14. Final Review - Complete
  15. Final Review - Payment Needed
  16. Final Review - Complete
  17. Plan Review - Reviewed

Contractors

  • Jason S Gonos

    Power Production Management Inc

    License
    CVC56764
    Title
    Solar Contractor
    Role
    Contractor
  • Aleksey Y Khokhlov

    Power Production Management

    License
    EC13008767
    Title
    Cert. Electrical
    Role
    Subcontractor

Inspections

  1. Oct 13, 2025

    Cancelled: Building - Footer

    Inspected by Tcrews

  2. Oct 13, 2025

    Cancelled: Solar - Thermal Plumbing Final

    Inspected by Tcrews

  3. Oct 14, 2025

    Passed: Solar - Solar Final

    Inspected by Gary Pitzer

  4. Oct 14, 2025

    Release to power company

    Inspected by Gary Pitzer

  5. Oct 14, 2025

    Passed: Electrical - Permanent Power

    Inspected by Gary Pitzer