| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
Footing Inspection Passed By Kevin Powell |
Private Provider |
7/7/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Plumbing Underground Passed By Kevin Powell |
Private Provider |
7/8/2025 |
| Passed: Building - Slab |
Slab Passed By Kevin Powell |
Private Provider |
7/11/2025 |
| Passed: Electrical - Temporary Service |
Temp Power Passed By Kevin Powell |
Private Provider |
7/15/2025 |
| Cancelled: Building - Footer |
|
Melissa Garber |
7/16/2025 |
| Cancelled: Engineering - Setbacks |
|
Melissa Garber |
7/16/2025 |
| Cancelled: Electrical - Temporary Service |
|
Melissa Garber |
7/16/2025 |
| Release to power company |
|
Private Provider |
7/16/2025 |
| Passed: Private Provider-Private Provider Inspection |
Roof Deck Passed By Kevin Powell |
Garber, Melissa |
8/4/2025 |
| Passed: Private Provider-Private Provider Inspection |
Wall Sheathing Passed By Kevin Powell |
Garber, Melissa |
8/4/2025 |
| Passed: Private Provider-Private Provider Inspection |
Ext Strapping / Wall Sheathing Passed By Kevin Powell |
Garber, Melissa |
8/4/2025 |
| Passed: Private Provider-Private Provider Inspection |
Framing Passed By Kevin Powell |
Garber, Melissa |
8/25/2025 |
| Passed: Private Provider-Private Provider Inspection |
Plumbing 2nd Rough Passed By Kevin Powell |
Garber, Melissa |
8/25/2025 |
| Passed: Private Provider-Private Provider Inspection |
Electrical 2nd Rough Passed By Kevin Powell |
Garber, Melissa |
8/25/2025 |
| Passed: Private Provider-Private Provider Inspection |
Footer Stell Grounding Passed By Kevin Powell |
Garber, Melissa |
8/25/2025 |
| Passed: Private Provider-Private Provider Inspection |
Mechanical Rough Passed By Kevin Powell |
Garber, Melissa |
9/22/2025 |
| Passed: Private Provider-Private Provider Inspection |
Insulation Passed By Kevin Powell |
Garber, Melissa |
9/22/2025 |
| (Requested) Engineering-Setbacks |
|
|
|
| (Requested) Building-Ext Strapping/Wall Sheathing |
|
|
|
| (Requested) Building-Roof Decking |
|
|
|
| (Requested) Building-Wall Sheathing |
|
|
|
| (Requested) Building-Framing |
|
|
|
| (Requested) Plumbing/Gas-2nd Rough-In |
|
|
|
| (Requested) Electrical -Footer Steel & Grounding |
|
|
|
| (Requested) Electrical -2nd Rough-In |
|
|
|
| (Requested) Building-Insulation |
|
|
|
| (Requested) Mechanical-Rough In |
|
|
|