5/30/2025
|
Application pending.
|
5/30/2025
|
Application submitted by applicant.
|
6/2/2025
|
Point Review - Printed-Online Application
NEED
* DESCRIPTION OF THE WORK BEING PERFORMED:
|
6/2/2025
|
Final Review - Corrections Needed
NEEDed:
*scope of work as to what is being completed
*product approval numbers (if applicable)
*proposed site plan (if window/door replacement)
*subform if any trades being completed
***prior to inspections***
recorded noc
|
6/3/2025
|
Final Review - Corrections Needed
NEEDED:
*SCOPE OF WORK AS TO WHAT IS BEING COMPLETED
*PRODUCT APPROVAL NUMBERS (IF APPLICABLE)
*PROPOSED SITE PLAN (IF WINDOW/DOOR REPLACEMENT)
*SUBFORM IF ANY TRADES BEING COMPLETED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
6/5/2025
|
Final Review - Corrections Needed
NEEDED:
*SCOPE OF WORK AS TO WHAT IS BEING COMPLETED
*PRODUCT APPROVAL NUMBERS (IF APPLICABLE)
*PROPOSED SITE PLAN (IF WINDOW/DOOR REPLACEMENT)
*SUBFORM IF ANY TRADES BEING COMPLETED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
6/6/2025
|
Final Review - Corrections Needed
NEEDED:
*PROPOSED SITE PLAN (IF WINDOW/DOOR REPLACEMENT)
*NOTICE TO BUILDING OFFICIAL OF PRIVATE PROVIDER
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
6/12/2025
|
Final Review - Corrections Needed
NEEDED:
*PROPOSED SITE PLAN (IF WINDOW/DOOR REPLACEMENT)
*NOTICE TO BUILDING OFFICIAL OF PRIVATE PROVIDER
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
6/16/2025
|
Final Review - Corrections Needed
NEEDED:
*PROPOSED SITE PLAN (IF WINDOW/DOOR REPLACEMENT)
*NOTICE TO BUILDING OFFICIAL OF PRIVATE PROVIDER
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
6/17/2025
|
Final Review - Payment Needed
|
6/18/2025
|
Permit Issued
Permit # created and approved from payment.
|
6/18/2025
|
Final Review - Complete
|