Permit Details

Permit Search

Permit

Mobile Home

125 SW ENDEAVOR CT
LAKE CITY, FL 32024

Permit #
000053384
Application #
71140
Status Completed
  1. Submitted May 21, 2025
  2. Issued Jun 16, 2025
  3. Expires Dec 24, 2025
  4. Completed Jun 27, 2025

Property

Parcel #
00210-001
Owner
Ccf Properties Llc
Acres
1.96
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
Bottom of lowest beam must be one foot above the road
Fema map number
12023C0260C
Mobile Home is a:
Single Wide
Year Built
1997
Width (Ft.In)
14
Length (Ft.In)
60
Driveway access to home:
Existing Drive
Installation Decal #
115001
Septic #
25-0454
Setbacks Front
30'
Setback Side 1
25'
Setbacks Rear
25'
Dev Permit #
F023-
Setback Side 2
25'
Are you applying for a 5 year temporary permit?
No
Serial #
h1340000g14
Wind Zone?
2
Residential or Commercial Use?
Residential
How many of bedrooms does this home have?
2
How many bathrooms does this home have?
2

Status & Review History

  1. Point Review - Processing
  2. Point Review - Reviewed
  3. Zoning Review - Reviewed
  4. Plan Review - Reviewed
  5. Final Review - Documents Required
  6. Final Review - Documents Required
  7. Final Review - Reviewed
  8. Final Review - Payment Needed
  9. Final Review - Payment Needed
  10. Permit Issued

Contractors

  • Jacob Trowell

    Trowell's Mobile Home Set Up Llc

    License
    IH1148380
    Title
    Mh Installer (ih)
    Role
    Contractor

Inspections

  1. May 30, 2025

    Passed: Mobile Home - In County Pre-Mobile Home before set-up

    Mobile Home Has Been Removed

    Inspected by Matt Forsyth

  2. Jun 10, 2025

    Septic Release Inspection

    Inspected by Health Dept

  3. Jun 27, 2025

    Passed: Certificate-Release Certificate

    Inspected by Matt Forsyth

  4. Jun 27, 2025

    Passed: Mobile Home - Mobile Home Set-Up Final

    Good Drainage Was Observed Along With Landings And Stairs Front And Back

    Inspected by Matt Forsyth

  5. Jun 27, 2025

    Release to power company

    Ok To Release Power-- 6.27.25 Mg

    Inspected by Matt Forsyth

  6. Jun 27, 2025

    Passed: Engineering - Setbacks

    Side Set Back Confirmed

    Inspected by Matt Forsyth

  7. Jun 27, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

Documents