Permit Details

Permit Search

Permit

New Commercial Construction

342 SE TYRE RD
LAKE CITY, FL 32025

Permit #
000053358
Application #
70233
Status Completed
  1. Submitted Apr 4, 2025
  2. Issued Jun 12, 2025
  3. Expires Nov 4, 2026
  4. Completed May 19, 2026

Property

Parcel #
10332-005
Owner
Bancroft Performance Investments Llc,
Acres
19.81
Subdivision
—
Zoning
MUD-I
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Not yet released
Related permit
—

Job Details

Elevation regulation
Site & Development Plan
Finished floor requirement
100'
Requirement needed
By Nailing Inspection
Document needed is
NA
Document receieved
No
Fema map number
12023C0320C
This is the construction of a:
Liquid Fertilizer Facility
Driveway access to property:
Existing Drive
Is there a Fire Sprinkler System?
No
Setbacks Front
20'
Setback Side 1
15'
Setback Side 2
15'
Setback Rear
15'
Describe commercial use:
AGROLiquid
Stories
1
Heated Area (Sqft)
2300
Total Area (Sqft)
36480
Building Height
26
Building Code Construction Type
II
Building Code Element
B
Building Code Occupancy Types
Business
Occupancy Use Title
Manufacturing, Office, Warehouse
Dev Permit #
F023-
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Sealed roof decking options. (Must select one.)
Other (explain)
Sealed roof decking explanation for other option.
part of metal building
Service Amps
2000

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Point Review - Printed-Online Application
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Plumbing Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Electrical Approved
  10. Plan Review - Building Approved
  11. Plan Review - Reviewed
  12. Final Review - Processing
  13. Final Review - Documents Required
  14. Final Review - Documents Required
  15. Final Review - Documents Required
  16. Final Review - Documents Required
  17. Final Review - Documents Required
  18. Final Review - Documents Required
  19. Final Review - Documents Required
  20. Zoning Review - Reviewed
  21. Final Review - Documents Required
  22. Final Review - Documents Required
  23. Final Review - Documents Required
  24. Final Review - Documents Required
  25. Final Review - Documents Required
  26. Final Review - Documents Required
  27. Final Review - Documents Required
  28. Final Review - Documents Required
  29. Final Review - Documents Required
  30. Final Review - Reviewed
  31. Final Review - Payment Needed
  32. Final Review - Payment Needed
  33. Permit Issued
  34. Final Review - Complete

Contractors

  • Eric Bender

    Greystone Construntion Company

    License
    CGC1534340
    Title
    Cert. General
    Role
    Contractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • James B Seay

    Miller Electric Company

    License
    EC13003061
    Title
    Cert. Electrical
    Role
    Subcontractor

Inspections

  1. Apr 7, 2025

    Passed: Fire - Plan Review

    Inspected by Cpt. Shane Overstreet

  2. Jun 5, 2025

    Rescheduled 6/6/2025:Building - Slab

    Inspected by Troy Crews

  3. Jun 6, 2025

    Passed: Building - Slab

    Partial Truck Slab And Interior 2 Matts Of Steel

    Inspected by Troy Crews

  4. Jun 9, 2025

    Passed: Building - Slab

    Nw Section

    Inspected by Troy Crews

  5. Jun 9, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Jun 9, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  7. Jun 11, 2025

    Passed: Building - Slab

    Middle Of Building Interior Slab

    Inspected by Troy Crews

  8. Jun 12, 2025

    Passed: Building - Slab

    3 Ramp Sections And More Interior Slab North East Side

    Inspected by Troy Crews

  9. Jun 13, 2025

    Passed: Building - Footer

    Done On 5-27-25 Footers

    Inspected by Troy Crews

  10. Jun 13, 2025

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  11. Jun 13, 2025

    Passed: Building - Masonry Wall Reinforcing

    Foundation Walls Partial

    Inspected by Troy Crews

  12. Jun 13, 2025

    Passed: Building - Masonry Wall Reinforcing

    Done 6-3-25 Foundation Walls

    Inspected by Troy Crews

  13. Jun 13, 2025

    Passed: Building - Slab

    Se Section Interior And Approach. Slab West Side

    Inspected by Troy Crews

  14. Jun 16, 2025

    Passed: Building - Slab

    Partial Interior And One Exterior

    Inspected by Troy Crews

  15. Jun 17, 2025

    Passed: Building - Slab

    Reminder Of Interior East End Of Building

    Inspected by Troy Crews

  16. Jun 20, 2025

    Passed: Building - Slab

    Tank Farm Slab 2 Foot With Two Mats Of Steel

    Inspected by Troy Crews

  17. Jul 11, 2025

    Passed: Building - Framing

    Bolts On Main Framing

    Inspected by Troy Crews

  18. Aug 13, 2025

    Rescheduled 8/14/2025:Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  19. Aug 14, 2025

    Passed: Plumbing/Gas - Water Pipe

    Partial 6 Inch Fire Line And 2 Inch Domestic Water

    Inspected by Troy Crews

  20. Sep 18, 2025

    Passed: Building - Framing

    Inspected by Troy Crews

  21. Sep 18, 2025

    Passed: Building - Insulation

    Inspected by Troy Crews

  22. Sep 23, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Metal Shell

    Inspected by Troy Crews

  23. Sep 23, 2025

    Passed: Fire - Fire Rated Wall

    First Layer Of Two Hour Wall On Interior Of Building

    Inspected by Troy Crews

  24. Sep 23, 2025

    Passed: Plumbing/Gas - Water Pipe

    Potable Water And Fire Line Partial

    Inspected by Troy Crews

  25. Oct 2, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  26. Oct 2, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  27. Nov 20, 2025

    Passed: Building - Fire Rated Wall

    Reminder Of Firewalls

    Inspected by Troy Crews

  28. Nov 20, 2025

    Passed: Mechanical - Rough In

    Offices In Bathroom Areas

    Inspected by Troy Crews

  29. Nov 20, 2025

    Passed: Electrical - Above Ceiling

    Offices In Bathroom Areas

    Inspected by Troy Crews

  30. Dec 19, 2025

    Passed: Electrical - Permanent Power

    Power To Be Turned On Temporarily There Will Be Another Final Inspection With The Permanent Generator Hookup Outside Cannot Release Power Until Driveway Permit Has Final Inspection.

    Inspected by Troy Crews

  31. Jan 6, 2026

    Release to power company

    Email Approval To Release Power-- 1.6.26 Mg

    Inspected by Mgarber

  32. Jan 6, 2026

    Release to power company

    Added Power Company-- Ok To Release Power-- 1.6.26 Mg

    Inspected by Mgarber

  33. Jan 6, 2026

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  34. May 6, 2026

    Passed: Fire - Fire Final

    Inspected by Cpt. S Overstreet

  35. May 8, 2026

    Passed: Building - Final

    *assessments Owed, Pending Direction On City Utilities-- 5.13.26 Mg

    Inspected by Troy Crews

  36. May 8, 2026

    Passed: Engineering - Zoning Final

    Inspected by Troy Crews

Documents