| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
7/15/2025 |
| Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
7/16/2025 |
| Passed: Building - Monolithic Slab |
Need Pictures Of Sleeves On Pipes In Footers |
Anthony Aslan |
7/17/2025 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
7/17/2025 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
7/29/2025 |
| Release to power company |
Ok To Release Temp Power-- 7.30.25 Mg |
Anthony Aslan |
7/29/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
7/30/2025 |
| Passed: Sheathing/Nailing - Wall |
|
Anthony Aslan |
8/18/2025 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
9/16/2025 |
| Passed: Mechanical - Rough In |
Nail Guards Dryer Pipe |
Anthony Aslan |
9/16/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
9/16/2025 |
| Rescheduled 9/25/2025:Building - Framing |
|
Nanderson |
9/23/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
9/25/2025 |
| Passed: Building - Framing |
Electrical Box In Master Not Made Up
in Garage Fridge Water Line And Electrical Wire With Red X's On Stud Needs Nail Guard |
Anthony Aslan |
9/25/2025 |
| Passed: Building - Insulation |
R-19 Walls, Spray Foam Attic |
Anthony Aslan |
10/2/2025 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Christian Allen |
12/19/2025 |
| Passed: Electrical - Permanent Power |
|
Christian Allen |
1/13/2026 |
| Release to power company |
|
Christian Allen |
1/13/2026 |
| Submitted Power Release through FPL Portal |
|
Ward, Emaleigh C. |
1/15/2026 |
| Septic Release Inspection |
|
Health Dept |
1/26/2026 |
| Passed: Building - Final |
All Requirements Met To Release Co-- 2.3.26 Mg |
Christian Allen |
2/3/2026 |