| Passed: Building - Footer |
|
Matt Forsyth |
6/27/2025 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
6/27/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Pipe |
Matt Forsyth |
7/22/2025 |
| Passed: Building - Slab |
Perimeter Bar Three Quarter Inch Clearance Minimum For Concrete Placement |
Matt Forsyth |
8/1/2025 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
9/18/2025 |
| Passed: Building - Framing |
|
Matt Forsyth |
10/31/2025 |
| Passed: Building - Strapping |
Bottom Of Post Base Nails To Be Simpson Approved |
Matt Forsyth |
10/31/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/6/2026 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/6/2026 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
1/6/2026 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/6/2026 |
| Passed: Building - Insulation |
|
Matt Forsyth |
1/20/2026 |
| (Requested) Building-Roof Decking |
|
|
|