Permit Details

Permit Search

Permit

New Residential Construction

345 SW BEACON WAY
LAKE CITY, FL 32025

Permit #
000053213
Application #
70340
Status Completed
  1. Submitted Apr 11, 2025
  2. Issued Feb 12, 2026
  3. Expires Oct 24, 2026
  4. Completed May 5, 2026

Property

Parcel #
02951-117
Owner
Graham Murvyn,
Acres
0.55
Subdivision
Amelia Landing Phase 1
Zoning
PRD
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Subdivision Plat
Finished floor requirement
115'
Requirement needed
By Nailing Inspection
Document needed is
Surveyor letter (FFE)
Document receieved
Yes
Fema map number
12023C0293D
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
2159
Total Area (Sqft)
3269
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
x-city
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Point Review - Processing
  5. Point Review - Printed-Online Application
  6. Plan Review - Documents Required
  7. Zoning Review - Processing
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Zoning Review - On Hold-Incomplete
  11. Plan Review - Plumbing Approved
  12. Plan Review - Mechanical Approved
  13. Plan Review - Electrical Approved
  14. Plan Review - Building Approved
  15. Plan Review - Reviewed
  16. Zoning Review - Processing
  17. Zoning Review - Reviewed
  18. Final Review - Reviewed
  19. Final Review - Payment Needed
  20. Permit Issued
  21. Final Review - Complete
  22. Permit Reissued
  23. Permit Status Update Notification
  24. Permit Status Update Notification

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Daniel Byrd

    Byrds Eye Roofing Inc

    License
    CCC1332899
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Jun 5, 2025

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  2. Jun 5, 2025

    Passed: Building - Footer

    2#5 On Chairs And Wired

    Inspected by Gary Pitzer

  3. Jun 5, 2025

    Passed: Electrical - Temporary Service

    Temp Pole Only

    Inspected by Gary Pitzer

  4. Jun 5, 2025

    Release to power company

    Inspected by Gary Pitzer

  5. Aug 7, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Aug 26, 2025

    Passed: Building - Slab

    Inspected by Anthony Aslan

  7. Sep 30, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Gary Pitzer

  8. Sep 30, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  9. Sep 30, 2025

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  10. Oct 9, 2025

    Passed: Building - Framing

    Inspected by Christian Allen

  11. Oct 9, 2025

    Passed: Building - Strapping

    Inspected by Christian Allen

  12. Oct 28, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Christian Allen

  13. Oct 28, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Christian Allen

  14. Oct 28, 2025

    Passed: Mechanical - Rough In

    Inspected by Christian Allen

  15. Oct 28, 2025

    Passed: Building - Window Attachment

    Inspected by Christian Allen

  16. Nov 5, 2025

    Passed: Building - Insulation

    Inspected by Christian Allen

  17. Jan 6, 2026

    Passed: Electrical - Permanent Power

    Inspected by Christian Allen

  18. Jan 6, 2026

    Release to power company

    Inspected by Christian Allen

  19. Mar 4, 2026

    Passed: Building - Monolithic Slab

    Inspected by Christian Allen

  20. Mar 10, 2026

    Passed: Electrical - Permanent Power

    Was For Temp Co

    Inspected by Christian Allen

  21. Mar 10, 2026

    Release to power company

    Inspected by Christian Allen

  22. Mar 11, 2026

    Cancelled: Building - Framing

    Already Done

    Inspected by Tcrews

  23. Mar 13, 2026

    Passed: Building - Framing

    Inspected by Troy Crews

  24. Mar 18, 2026

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City Distribution And Collections Department

  25. Apr 27, 2026

    Passed: Building - Final

    Inspected by Christian Allen

Documents