Permit Details

Permit Search

Permit

New Residential Construction

348 SW LEGREE TER
FORT WHITE, FL 32038

Permit #
000053135
Application #
70260
Status Completed
  1. Submitted Apr 7, 2025
  2. Issued May 19, 2025
  3. Expires Mar 22, 2027
  4. Completed Oct 20, 2026

Property

Parcel #
04076-143
Owner
Yunck Randall, Yunck Joanne
Acres
5.00
Subdivision
Parker Woods
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
12" above adjacent ground for entire perimeter
Fema map number
12023C0495C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1733
Total Area (Sqft)
3110
Building Height
17
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0404
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Corrections Needed
  6. Plan Review - Corrections Needed
  7. Plan Review - Building Approved
  8. Plan Review - Electrical Approved
  9. Plan Review - Mechanical Approved
  10. Plan Review - Plumbing Approved
  11. Plan Review - Fuel/Gas Approved
  12. Plan Review - Reviewed
  13. Zoning Review - Reviewed
  14. Final Review - Documents Required
  15. Final Review - Reviewed
  16. Final Review - Payment Needed
  17. Permit Issued
  18. Final Review - Complete

Contractors

This is an owner-builder project.

Inspections

  1. Apr 5, 2024

    Septic Release Inspection

    Inspected by Health Dept

  2. Jun 2, 2025

    Passed: Building - Footer

    Inspected by Anthony Aslan

  3. Jun 2, 2025

    Passed: Engineering - Setbacks

    Appears Within Setbacks

    Inspected by Anthony Aslan

  4. Jun 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  5. Jun 26, 2025

    Passed: Building - Slab

    Inspected by Anthony Aslan

  6. Jun 26, 2025

    Cancelled: Building - Monolithic Slab

    Inspected by Anthony Aslan

  7. Jun 26, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  8. Jul 15, 2025

    Passed: Building - Monolithic Slab

    Porches On House

    Inspected by Anthony Aslan

  9. Jul 15, 2025

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  10. Aug 7, 2025

    Cancelled: Building - Strapping

    Inspected by Anthony Aslan

  11. Aug 7, 2025

    Cancelled: Building - Wall Sheathing

    Inspected by Anthony Aslan

  12. Aug 8, 2025

    Cancelled: Building - Framing

    Inspected by Anthony Aslan

  13. Aug 8, 2025

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  14. Aug 8, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Need Pictures Of Gable Flat Straps

    Inspected by Anthony Aslan

  15. Aug 22, 2025

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Anthony Aslan

  16. Aug 22, 2025

    Passed: Building - Framing

    Inspected by Anthony Aslan

  17. Aug 22, 2025

    Cancelled: Building - Strapping

    Inspected by Anthony Aslan

  18. Aug 22, 2025

    Cancelled: Building - Window Attachment

    Inspected by Anthony Aslan

  19. Nov 17, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Christian Allen

  20. Nov 17, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Christian Allen

  21. Nov 19, 2025

    Passed: Mechanical - Rough In

    Inspected by Christian Allen

  22. Jan 13, 2026

    Passed: Building - Insulation

    Inspected by Christian Allen

  23. Jan 13, 2026

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Christian Allen

  24. Jan 13, 2026

    Passed: Building - Wall Sheathing

    Inspected by Christian Allen

  25. Jan 13, 2026

    Passed: Building - Window Attachment

    Inspected by Christian Allen

  26. Apr 22, 2026

    Passed: Electrical - Permanent Power

    Inspected by Christian Allen

  27. Apr 22, 2026

    Release to power company

    Inspected by Christian Allen

  28. Sep 23, 2026

    Passed: Building - Final

    Inspected by Christian Allen

Documents