1/24/2025
|
Point Review - Received-Hard Copy Application
NEED
*SEALED METAL BUILDING PLANS
*PRODUCT APPROVAL CODES
|
1/24/2025
|
Point Review - Reviewed
NEED
*SEALED METAL BUILDING PLANS
*PRODUCT APPROVAL CODES
|
1/27/2025
|
Zoning Review - Documents Required
NEED
*SEALED METAL BUILDING PLANS
*PRODUCT APPROVAL CODES
ZONING: SPECIAL FLOOD HAZARD AREA WITH A REQUIREMENT OF 36' ELEVATION OR FLOOD VENTS REQUIRED.
* PLEASE PROVIDE A ZERO RISE CERTIFICATE/LETTER FROM AN ENGINEER SINCE THE FILL DIRT HAS BEEN BROUGHT IN.
* COMPACTION REPORT PRIOR TO THE SLAB BEING POURED.
* CONSTRUCTION DRAWING BASED ELEVATION CERTIFICATE PRIOR TO PERMIT ISSUANCE -INCLUDE FLOOD VENT CALCULATIONS AND PRODUCT INFORMATION
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
3/11/2025
|
Zoning Review - Documents Required
NEED
*SEALED METAL BUILDING PLANS
*PRODUCT APPROVAL CODES
ZONING: SPECIAL FLOOD HAZARD AREA WITH A REQUIREMENT OF 36' ELEVATION OR FLOOD VENTS REQUIRED.
* PLEASE PROVIDE A ZERO RISE CERTIFICATE/LETTER FROM AN ENGINEER SINCE THE FILL DIRT HAS BEEN BROUGHT IN.
* CONSTRUCTION DRAWING BASED ELEVATION CERTIFICATE PRIOR TO PERMIT ISSUANCE -INCLUDE FLOOD VENT CALCULATIONS AND PRODUCT INFORMATION
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
4/3/2025
|
Zoning Review - Documents Required
NEED
*SEALED METAL BUILDING PLANS
*PRODUCT APPROVAL CODES
ZONING: SPECIAL FLOOD HAZARD AREA WITH A REQUIREMENT OF 36' ELEVATION OR FLOOD VENTS REQUIRED.
* PLEASE PROVIDE A ZERO RISE CERTIFICATE/LETTER FROM AN ENGINEER SINCE THE FILL DIRT HAS BEEN BROUGHT IN.
* CONSTRUCTION DRAWING BASED ELEVATION CERTIFICATE PRIOR TO PERMIT ISSUANCE -INCLUDE FLOOD VENT CALCULATIONS AND PRODUCT INFORMATION
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
4/21/2025
|
Plan Review - Reviewed
NEED
ZONING: SPECIAL FLOOD HAZARD AREA WITH A REQUIREMENT OF 36' ELEVATION OR FLOOD VENTS REQUIRED.
* PLEASE PROVIDE A ZERO RISE CERTIFICATE/LETTER FROM AN ENGINEER SINCE THE FILL DIRT HAS BEEN BROUGHT IN.
* CONSTRUCTION DRAWING BASED ELEVATION CERTIFICATE PRIOR TO PERMIT ISSUANCE -INCLUDE FLOOD VENT CALCULATIONS AND PRODUCT INFORMATION
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
4/22/2025
|
Zoning Review - Documents Required
NEED
ZONING: SPECIAL FLOOD HAZARD AREA WITH A REQUIREMENT OF 36.2' ELEVATION OR FLOOD VENTS REQUIRED.
* PLEASE PROVIDE A ZERO RISE CERTIFICATE/LETTER FROM AN ENGINEER SINCE THE FILL DIRT HAS BEEN BROUGHT IN.
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
4/28/2025
|
Zoning Review - Reviewed
NEED
* FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
4/28/2025
|
Final Review - Corrections Needed
NEEDED:
*FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
**APPLICATION TO BE INVOICED ONCE FDP PAYMENT HAS BEEN REC'D-- 4.28.25 MG
|
5/12/2025
|
Final Review - Payment Needed
NEEDED:
*FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|
5/12/2025
|
Permit Issued
Permit #000053090 created and approved.
|
5/19/2025
|
Final Review - Complete
NEEDED:
*FINAL CONSTRUCTION ELEVATION CERTIFICATE PRIOR TO FINAL INSPECTION - INCLUDE PHOTOS OF ALL SIDES OF THE BLGD WITH VENTS.
|