Permit Details

Permit Search

Permit

New Residential Construction

424 SW SILVER PALM DR
LAKE CITY, FL 32024

Permit #
000053079
Application #
70403
Status Completed
  1. Submitted Apr 15, 2025
  2. Issued Jun 22, 2025
  3. Expires Jun 1, 2026
  4. Completed Dec 4, 2025

Property

Parcel #
02731-077
Owner
Adams Homes Of Northwest Florida, Inc,
Acres
0.25
Subdivision
Preserve At Laurel Lake Unit 1
Zoning
PRD
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
117.3'
Requirement needed
By Nailing Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
Yes
Fema map number
12023C0290D
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
1816
Total Area (Sqft)
2397
Building Height
18
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
x-city
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Point Review - Processing
  5. Plan Review - Plumbing Approved
  6. Plan Review - Mechanical Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Building Approved
  9. Plan Review - Reviewed
  10. Zoning Review - Processing
  11. Zoning Review - Reviewed
  12. Final Review - Corrections Needed
  13. Final Review - Reviewed
  14. Final Review - Payment Needed
  15. Final Review - Payment Needed
  16. Permit Issued
  17. Permit Reissued

Contractors

  • William Adams

    Adams Homes Of Northwest Florida Inc

    License
    CRC1330146
    Title
    Cert. Residential
    Role
    Contractor
  • Shawn Reynolds

    Ncf Electrical Services Llc

    License
    EC13011927
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Derrick L Williams

    D L Williams Heating & Cooling Llc

    License
    CAC1816913
    Title
    Class "b" A/c Contractor
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Benjamin T Keeler

    Keeler Roofing, Llc

    License
    CCC1330509
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Jun 4, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Troy Crews

  2. Jun 9, 2025

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  3. Jun 9, 2025

    Passed: Engineering - Setbacks

    Surveyor To Confirm Setbacks

    Inspected by Troy Crews

  4. Jul 7, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  5. Jul 7, 2025

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  6. Jul 7, 2025

    Passed: Building - Strapping

    Inspected by Troy Crews

  7. Jul 11, 2025

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Troy Crews

  8. Jul 11, 2025

    Passed: Building - Framing

    Inspected by Troy Crews

  9. Jul 11, 2025

    Cancelled: Building - Strapping

    Inspected by Troy Crews

  10. Jul 11, 2025

    Cancelled: Building - Wall Sheathing

    Inspected by Troy Crews

  11. Jul 11, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Troy Crews

  12. Jul 11, 2025

    Passed: Mechanical - Rough In

    Inspected by Troy Crews

  13. Jul 11, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  14. Jul 11, 2025

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Troy Crews

  15. Jul 17, 2025

    Passed: Building - Insulation

    Walls R-13, Vault R-30, Knee Walls R-19

    Inspected by Anthony Aslan

  16. Aug 22, 2025

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  17. Aug 22, 2025

    Release to power company

    Final Drive Rec'd 8.28.25-- Mg

    Inspected by Troy Crews

  18. Sep 1, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  19. Dec 1, 2025

    Passed: Building - Final

    All Requirements Met To Release Co-- 12.4.25 Mg

    Inspected by Troy Crews

  20. Dec 3, 2025

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City Distribution And Collections Department

Documents