- Elevation regulation
- Site & Development Plan
- Finished floor requirement
- 104.2'
- Requirement needed
- By Nailing Inspection
- Document needed is
- a Surveyor letter giving the Finished Floor Elevation
- Document receieved
- No
- Fema map number
- 12023C0293D
- This is the construction of a:
- church
- Driveway access to property:
- Driveway permit
- Is there a Fire Sprinkler System?
- No
- Setbacks Front
- 25'
- Setback Side 1
- 10'
- Setback Side 2
- 10'
- Setback Rear
- 15'
- Describe commercial use:
- for trinity faith outreach ministries project
- Stories
- 1
- Heated Area (Sqft)
- 2400
- Total Area (Sqft)
- 2400
- Building Height
- 15
- Building Code Construction Type
- I
- Building Code Element
- B
- Building Code Occupancy Types
- Assembly
- Occupancy Use Title
- church
- Dev Permit #
- F023-
- Building Code Edition
- 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
- Septic# (00-0000) or (X00-000)
- 25-0293
- Sealed roof decking options. (Must select one.)
- Other (explain)
- Sealed roof decking explanation for other option.
- part of metal building
- Service Amps
- 200