Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
4/25/2025 |
Release to power company |
|
Matt Forsyth |
4/25/2025 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Water Supply Under Slab |
Matt Forsyth |
5/1/2025 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
5/6/2025 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
5/6/2025 |
Passed: Building - Masonry Wall Reinforcing |
Clean Outs Inspected |
Matt Forsyth |
5/15/2025 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
5/21/2025 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
5/21/2025 |
Passed: Building - Framing |
Concrete Lentil Ties For Roof Framing |
Matt Forsyth |
5/28/2025 |
Passed: Electrical - 1st Underground Rough–In |
2nd Rough |
Matt Forsyth |
6/5/2025 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
6/5/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
6/6/2025 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
6/6/2025 |
Passed: Building - Insulation |
Walls And Garage To Habitable Dwelling |
Matt Forsyth |
6/9/2025 |
Septic Release Inspection |
|
Health Dept |
6/20/2025 |
Cancelled: Electrical - 2nd Rough-In |
|
Matt Forsyth |
7/8/2025 |
Passed: Electrical - Permanent Power |
Drive Rec'd |
Matt Forsyth |
7/10/2025 |
Release to power company |
|
Mgarber |
7/16/2025 |
Failed: Building - Final |
Need To Complete Repairs Around Exterior Outlet Boxes Double Vanity Bathroom Needs An Additional Outlet Or The Outlet Needs To Be Centered |
Troy Crews |
7/25/2025 |
Passed: Building - Final |
All Requirements Met To Release Co-- 7.29.25 Mg |
Matt Forsyth |
7/29/2025 |