Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 583 SW CHESTERFIELD CIR
LAKE CITY, FL 32024
Parcel #: 03117-154
Acres: 0.52
Owner: Delta Omega Properties Inc ; Rhett Smithey
Subdivision: Crosswinds Phase 2
Zoning: RSF-2
Flood Zone: X
District: 3
Application #: 69456
Permit #: 000052632
Related Permit:
Submitted: Wednesday, February 26, 2025
Issued: Tuesday, March 18, 2025
Expires: Sunday, February 15, 2026
Completed:
Status: Final Review - Complete
Septic Release? No
Notes:
*MFE = 1' ABOVE THE ROAD
Job Details
Finished floor requirement
Fema map number 12023C0195D
Type of Structure House
Commercial or Residential? Residential
Description of the work being performed: Foundation Repair
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Dev Permit # F023-
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Service Amps 0
Review Notes
2/13/2025 Application pending.
2/26/2025 Application submitted by applicant.
2/27/2025 Point Review - Processing
3/9/2025 Point Review - Printed-Online Application
3/9/2025 Point Review - Reviewed
3/9/2025 Zoning Review - Reviewed
3/9/2025 Plan Review - Documents Required
3/12/2025 Plan Review - Documents Required
3/12/2025 Plan Review - Documents Required
3/14/2025 Plan Review - Plumbing Approved
3/14/2025 Plan Review - Mechanical Approved
3/14/2025 Plan Review - Electrical Approved
3/14/2025 Plan Review - Building Approved
3/14/2025 Plan Review - Reviewed
3/14/2025 Final Review - Processing
3/14/2025 Final Review - Reviewed
3/14/2025 Final Review - Payment Needed
3/18/2025 Permit Issued
8/29/2025 Final Review - Complete
Contractors
Name/ Business License Title Role
Brian T Giebeig
Trent Giebeig Construction,inc.
CRC1330693 Residential Contractor Contractor
Kenneth R Roche
Ken Roche Plumbing Inc Dba Plumbing Now
CFC1426527 Plumbing Contractor Subcontractor
Everton D Ruddock
D&s Lighting Inc
EC13003800 Electrical Contractor Subcontractor
Derrick L Williams
D L Williams Heating & Cooling Llc
CAC1816913 Class "b" A/c Contractor Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Setbacks Gary Pitzer 3/19/2025
Passed: Building - Footer Gary Pitzer 3/19/2025
Passed: Plumbing/Gas - 2nd Rough-In Gary Pitzer 3/31/2025
Cancelled: Plumbing/Gas - 2nd Rough-In Gary Pitzer 4/1/2025
Passed: Building - Slab Send In Termite Report, Not In Box Gary Pitzer 4/3/2025
Rescheduled 5/2/2025:Building - Roof Decking Gary Pitzer 5/1/2025
Rescheduled 5/2/2025:Building - Wall Sheathing Gary Pitzer 5/1/2025
Passed: Building - Roof Decking Gary Pitzer 5/2/2025
Passed: Building - Wall Sheathing Gary Pitzer 5/2/2025
Passed: Building - Framing Gary Pitzer 5/28/2025
Passed: Electrical - 2nd Rough-In Gary Pitzer 5/28/2025
Passed: Mechanical - Rough In Gary Pitzer 5/28/2025
Passed: Plumbing/Gas - 2nd Rough-In Gary Pitzer 5/28/2025
Failed: Building - Insulation Not Ready Rescheduled For 6/11/25 Gary Pitzer 6/10/2025
Passed: Building - Insulation Wall Batts Gary Pitzer 6/11/2025
Release to power company House Will Be On City Sewer Tcrews 8/19/2025
Passed: Electrical - Permanent Power Need Septic Release Anthony Aslan 8/19/2025
Documents
File Name Date File Size