Permit Details

Permit Search

Permit

New Residential Construction

271 SW BLAYLOCK CT
LAKE CITY, FL 32024

Permit #
000052586
Application #
69457
Status Completed
  1. Submitted Feb 13, 2025
  2. Issued Mar 14, 2025
  3. Expires Jul 15, 2026
  4. Completed Jan 16, 2026

Property

Parcel #
03401-009
Owner
Raymont Melissa, Raymont Paul Owen
Acres
4.99
Subdivision
Rivers Manor Unit 2 Unr
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0383D
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2370
Total Area (Sqft)
3642
Building Height
24
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
25-0170
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Processing
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Zoning Review - Reviewed
  7. Plan Review - Building Approved
  8. Plan Review - Electrical Approved
  9. Plan Review - Mechanical Approved
  10. Plan Review - Plumbing Approved
  11. Plan Review - Fuel/Gas Approved
  12. Plan Review - Reviewed
  13. Final Review - Payment Needed
  14. Permit Issued

Contractors

  • Isaiah Cully

    Ic Construction Llc

    License
    CBC1259655
    Title
    Building Contractor
    Role
    Contractor
  • Clinton G Wilson

    Wilson Heat & Air Inc

    License
    CAC057886
    Title
    Class B A/c
    Role
    Subcontractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Tyler M Turner

    Tmt Roofing Llc

    License
    CCC1330410
    Title
    Cert Roofing
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor

Inspections

  1. Mar 21, 2025

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  2. Mar 21, 2025

    Passed: Building - Footer

    2#5 Wired And On Chairs Electric Bond

    Inspected by Gary Pitzer

  3. Mar 24, 2025

    Passed: Electrical - Temporary Service

    Inspected by Gary Pitzer

  4. Mar 24, 2025

    Release to power company

    Inspected by Gary Pitzer

  5. Apr 16, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Gary Pitzer

  6. Apr 21, 2025

    Passed: Building - Slab

    Inspected by Anthony Aslan

  7. May 28, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  8. May 28, 2025

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  9. Jul 9, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  10. Jul 9, 2025

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  11. Jul 9, 2025

    Passed: Building - Framing

    Inspected by Gary Pitzer

  12. Jul 18, 2025

    Failed: Building - Insulation

    No Plumbing Inspection, Master Shower Valve Not Installed data Wires Not Foamed At Top Plate

    Inspected by Anthony Aslan

  13. Jul 21, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Valve Installed

    Inspected by Anthony Aslan

  14. Jul 21, 2025

    Passed: Building - Insulation

    Data Wire Foamed

    Inspected by Anthony Aslan

  15. Nov 4, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Gary Pitzer

  16. Dec 11, 2025

    Release to power company

    Inspected by Ewilliams

  17. Dec 11, 2025

    Septic Release Inspection

    Inspected by Health Dept

  18. Jan 13, 2026

    Failed: Building - Final

    Need To Complete. Stove Top And Hood Vent, Install Outlets In Kitchen, Front Door Locks, Blower Door. Test Does Not Include Gas Inspection, By Contractor And Gas Supplier.

    Inspected by Troy Crews

  19. Jan 15, 2026

    Passed: Building - Final

    Inspected by Troy Crews

  20. Jan 16, 2026

    Passed: Certificate - Release Certificate

    Inspected by Crews, Malcolm T.

Documents