2/5/2025
|
Application pending.
|
2/5/2025
|
Application submitted by applicant.
|
2/5/2025
|
Point Review - Processing
NEED
* TAMMY BRAMLITT PENDING PAYMENT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN CONTACT THEM AT 386-758-1058
* FLOODPLAIN ORDINANCE NOTICE TO OWNER
* METAL BUILDING PLANS
* SUBCONTRACTOR FORM
|
2/28/2025
|
Point Review - On Hold-Incomplete
NEEDED
* IN THE ONLINE PORTAL UNDER THE JOB DETAILS SECTION THE PROPER SITE PLAN SETBACKS NEED TO BE INPUT - 10' WAS SELECTED FOR ALL SETBACKS AND THAT DOES NOT MATCH THE SITE PLAN. PLEASE CORRECT THIS AND HIT SAVE MY CHANGES
* DRIVE APPLICATION TO BE COMPLETED
* PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION
|
2/28/2025
|
Point Review - On Hold-Incomplete
NEEDED
* IN THE ONLINE PORTAL UNDER THE JOB DETAILS SECTION THE PROPER SITE PLAN SETBACKS NEED TO BE INPUT - 10' WAS SELECTED FOR ALL SETBACKS AND THAT DOES NOT MATCH THE SITE PLAN. PLEASE CORRECT THIS AND HIT SAVE MY CHANGES
* DRIVE APPLICATION TO BE COMPLETED
* PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION
* FL PRODUCT APPROVAL FOR ALL EXTERIOR DOORS AND WINDOWS
|
3/3/2025
|
Point Review - Printed-Online Application
NEEDED
* DRIVE APPLICATION TO BE COMPLETED
* PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/3/2025
|
Point Review - Reviewed
NEEDED
* DRIVE APPLICATION TO BE COMPLETED
* PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/3/2025
|
Zoning Review - Reviewed
NEEDED
* DRIVE APPLICATION TO BE COMPLETED
* PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/4/2025
|
Plan Review - Documents Required
NEEDED:
* DRIVE APPROVAL-- SEE APP #69696
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/4/2025
|
Plan Review - Documents Required
NEEDED:
*DRIVE APPROVAL-- SEE APP #69696
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/7/2025
|
Plan Review - Documents Required
NEEDED:
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/7/2025
|
Plan Review - Documents Required
NEEDED:
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/7/2025
|
Plan Review - On Hold-Incomplete
NEEDED:
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/10/2025
|
Plan Review - Documents Required
NEEDED:
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
|
3/10/2025
|
Zoning Review - Corrections Needed
NEEDED:
*PLANS TO BE SEALED BY ARCHITECT OR ENGINEER - ON HOLD UNTIL RECEIVED - NEED TO ALSO REFER TO 2023 BUILDING CODE/8TH ADDITION--- PLANS RECEIVED ARE NOT SEALED
*UPDATED SITE PLAN TO MEET 50' FRONT, SIDE, AND REAR SETBACK PER SUBDIVISION PLAT
|
3/11/2025
|
Plan Review - Building Approved
NEEDED:
*UPDATED SITE PLAN TO MEET 50' FRONT, SIDE, AND REAR SETBACK PER SUBDIVISION PLAT
|
3/11/2025
|
Plan Review - Reviewed
NEEDED:
*UPDATED SITE PLAN TO MEET 50' FRONT, SIDE, AND REAR SETBACK PER SUBDIVISION PLAT
|
3/11/2025
|
Zoning Review - Documents Required
NEEDED:
*UPDATED SITE PLAN TO MEET 50' FRONT, SIDE, AND REAR SETBACK PER SUBDIVISION PLAT
|
3/13/2025
|
Zoning Review - Reviewed
|
3/13/2025
|
Final Review - Reviewed
|
3/13/2025
|
Final Review - Payment Needed
|
3/13/2025
|
Permit Issued
Permit # created and approved from payment.
|