| Inspection |
Notes |
Performed By |
Date |
| Passed: Fire - Plan Review |
|
Cpt. Shane Overstreet |
2/11/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/19/2025 |
| Passed: Building - Slab |
Partial Mono Slab In Shop Area |
Troy Crews |
3/25/2025 |
| Passed: Building - Slab |
Main Part Of Building Offices And Shop Mono Slab |
Troy Crews |
3/27/2025 |
| Rescheduled 4/10/2025:Building - Slab |
|
Troy Crews |
4/2/2025 |
| Rescheduled 4/3/2025:Building - Slab |
|
Troy Crews |
4/2/2025 |
| Passed: Building - Slab |
Partial Near Shop Area. |
Troy Crews |
4/3/2025 |
| Passed: Building - Fire Rated Wall |
First Layer Of 5/8 On Office Side |
Troy Crews |
7/3/2025 |
| Passed: Building - Slab |
|
Troy Crews |
7/11/2025 |
| Passed: Electrical - 2nd Rough-In |
Front Office Areas |
Troy Crews |
7/23/2025 |
| Passed: Mechanical - Rough In |
Front Office Areas |
Troy Crews |
7/23/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Front Office Areas |
Troy Crews |
7/23/2025 |
| Passed: Building - Framing |
|
Troy Crews |
7/23/2025 |
| Release to power company |
|
Tcrews |
10/20/2025 |
| Rescheduled 10/20/2025:Electrical - Permanent Power |
|
Tcrews |
10/20/2025 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
10/20/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
10/20/2025 |
| Release to power company |
|
Tcrews |
12/2/2025 |
| Passed: Electrical - Permanent Power |
Changed Electric Service From Ct Setup To Conventional Meter Can |
Troy Crews |
12/2/2025 |
| Release to power company |
Ok To Release Power-- 12.2.25 Mg |
Troy Crews |
12/2/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
12/2/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
12/2/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
12/2/2025 |
| Passed: Engineering - Zoning Final |
|
Troy Crews |
1/7/2026 |
| Passed: Building - Final |
Need Fee Final Also Handicapp Sign At Parking Spot |
Troy Crews |
1/7/2026 |
| Passed: Fire - Fire Final |
|
Cpt. Shane Overstreet |
1/7/2026 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
1/8/2026 |
| Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
1/8/2026 |
| Passed: Certificate - Release Certificate |
Signs Posted On Hc Parking |
Crews, Malcolm T. |
1/9/2026 |
| Passed: Certificate - Release Certificate |
|
Crews, Malcolm T. |
1/9/2026 |