| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
|
Matt Forsyth |
3/5/2025 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
3/5/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
4/15/2025 |
| Failed: Building - Slab |
All Vertical Lap Bar Block Wall Missing |
Matt Forsyth |
4/25/2025 |
| Passed: Building - Slab |
Item Addressed |
Matt Forsyth |
4/28/2025 |
| Passed: Building - Lintel/Tie Beam |
Vertical Bar In Place For Continuation Of Block |
Matt Forsyth |
5/9/2025 |
| Passed: Building - Masonry Wall Reinforcing |
All Clean Outs Inspected |
Matt Forsyth |
5/9/2025 |
| Passed: Building - Lintel/Tie Beam |
Block And Bar Are In Place |
Matt Forsyth |
6/4/2025 |
| Passed: Building - Masonry Wall Reinforcing |
All Clean Outs Had Continuation Bar Too Lentil |
Matt Forsyth |
6/4/2025 |
| Passed: Building - Framing |
|
Matt Forsyth |
7/10/2025 |
| Passed: Building - Framing |
Temporary Railing |
Matt Forsyth |
7/24/2025 |
| Passed: Electrical - 2nd Rough-In |
Nail Plates |
Matt Forsyth |
7/24/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
7/24/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Shower Pan Installation Needed |
Matt Forsyth |
7/24/2025 |
| Passed: Building - Insulation |
All Walls All Floor Cavities Partial Ceiling |
Matt Forsyth |
7/31/2025 |
| Passed: Electrical - Permanent Power |
|
Gary Pitzer |
9/22/2025 |
| Release to power company |
|
Gary Pitzer |
9/22/2025 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
2nd Floor Shower Flooded |
Gary Pitzer |
9/22/2025 |
| Release to power company |
Rec'd Septic |
Ewilliams |
10/10/2025 |
| Septic Release Inspection |
|
Health Dept |
10/10/2025 |
| Passed: Building - Final |
Picture Of Condensate Line Minimum 12 Inches Away From The Wall Also Blower Door Test |
Matt Forsyth |
11/6/2025 |