Permit Details

Permit Search

Permit

New Residential Construction

299 SW BRYCE TER
FORT WHITE, FL 32038

Permit #
000052449
Application #
68998
Status Completed
  1. Submitted Jan 15, 2025
  2. Issued Feb 27, 2025
  3. Expires Mar 10, 2026
  4. Completed Jan 23, 2026

Property

Parcel #
03954-001
Owner
Parnell Shaun Aaron, Parnell Tammy Lynn
Acres
9.88
Subdivision
—
Zoning
—
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0490C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2115
Total Area (Sqft)
3343
Building Height
8
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0921
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Corrections Needed
  6. Zoning Review - Corrections Needed
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Zoning Review - Town of Ft. White
  11. Plan Review - Documents Required
  12. Plan Review - Plumbing Approved
  13. Plan Review - Mechanical Approved
  14. Plan Review - Electrical Approved
  15. Plan Review - Building Approved
  16. Plan Review - Reviewed
  17. Final Review - Processing
  18. Final Review - Reviewed
  19. Final Review - Payment Needed
  20. Permit Issued
  21. Final Review - Payment Needed

Contractors

This is an owner-builder project.

  • Lewis G Walker

    Lewis Walker Roofing Inc

    License
    CCC1333551
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Mar 14, 2025

    Passed: Electrical - Temporary Service

    Need Gfi Outlet

    Inspected by Anthony Aslan

  2. Mar 14, 2025

    Release to power company

    Inspected by Anthony Aslan

  3. Mar 26, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Gary Pitzer

  4. Apr 8, 2025

    Cancelled: Building - Footer

    Inspected by Emaleigh Williams

  5. Apr 8, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Emaleigh Williams

  6. Apr 9, 2025

    Cancelled: Building - Footer

    Inspected by Anthony Aslan

  7. Apr 9, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Anthony Aslan

  8. Apr 10, 2025

    Passed: Building - Monolithic Slab

    Inspected by Anthony Aslan

  9. Apr 10, 2025

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  10. Jun 3, 2025

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  11. Jun 3, 2025

    Passed: Building - Wall Sheathing

    Exterior Strapping Complete

    Inspected by Anthony Aslan

  12. Jun 3, 2025

    Cancelled: Building - Framing

    Inspected by Anthony Aslan

  13. Jun 5, 2025

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Anthony Aslan

  14. Jun 5, 2025

    Passed: Building - Framing

    Inspected by Anthony Aslan

  15. Jul 2, 2025

    Cancelled: Building - Roof Decking

    Inspected by Anthony Aslan

  16. Jul 2, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  17. Jul 2, 2025

    Passed: Mechanical - Rough In

    Inspected by Anthony Aslan

  18. Jul 2, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  19. Jul 8, 2025

    Passed: Building - Insulation

    Spray Foam Attic, R-19 Walls

    Inspected by Anthony Aslan

  20. Sep 3, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Anthony Aslan

  21. Sep 11, 2025

    Passed: Building - Final

    Septic Release Required Prior To Release Of Power And Co-- 12.16.25 Mg

    Inspected by Anthony Aslan

  22. Jan 23, 2026

    Release to power company

    Rec'd Septic

    Inspected by Ewilliams

  23. Jan 23, 2026

    Septic Release Inspection

    Inspected by Health Dept

Documents