Inspection |
Notes |
Performed By |
Date |
Passed: Building-Footer |
Passed By Seth Green |
Private Provider |
3/6/2025 |
Passed: Private Provider-Private Provider Inspection |
Plumbing Rough/top Out Passed By Seth Green |
Private Provider |
3/26/2025 |
Building-Slab |
Structural Slab Passed By Seth Green |
Private Provider |
4/2/2025 |
Building-Lintel/Tie Beam |
Lintel Tie Beam Passed By Seth Green |
Private Provider |
4/16/2025 |
Building-Roof Decking |
Roof Sheathing Passed By Seth Green |
Private Provider |
5/5/2025 |
Passed: Building-Framing |
Framing Passed By Seth Green |
Private Provider |
6/5/2025 |
Passed: Private Provider-Private Provider Inspection |
Electrical Rough Passed By Seth Green |
Private Provider |
6/5/2025 |
Passed: Private Provider-Private Provider Inspection |
Mechanical Rough Passed By Seth Green |
Private Provider |
6/5/2025 |
Passed: Private Provider-Private Provider Inspection |
Plumbing Rough/top Out Passed By Seth Green |
Private Provider |
6/5/2025 |
Passed: Private Provider-Private Provider Inspection |
Window Attachment Passed By Seth Green |
Private Provider |
6/5/2025 |
Passed: Building-Insulation |
Insulation Passed By Seth Green |
Private Provider |
6/26/2025 |
Passed: Private Provider-Private Provider Inspection |
Drywall Attachment (wall And Ceiling) Passed By Steven Sapp |
Private Provider |
7/2/2025 |
Septic Release Inspection |
|
Health Dept |
7/9/2025 |
Passed: Private Provider-Private Provider Inspection |
Backer Board Passed By Seth Green |
Private Provider |
8/5/2025 |
Passed: Private Provider-Private Provider Inspection |
Semi Perm Pased By Seth Green |
Private Provider |
8/19/2025 |
Release to power company |
|
Mgarber |
8/27/2025 |