| 1/23/2025 |
Application pending. |
| 1/23/2025 |
Application submitted by applicant. |
| 2/7/2025 |
Point Review - Printed-Online Application |
| 2/7/2025 |
Point Review - Reviewed |
| 2/7/2025 |
Zoning Review - Reviewed |
| 2/7/2025 |
Plan Review - Documents Required |
| 2/10/2025 |
Plan Review - Documents Required |
| 2/14/2025 |
Plan Review - Plumbing Approved |
| 2/14/2025 |
Plan Review - Mechanical Approved |
| 2/14/2025 |
Plan Review - Electrical Approved |
| 2/14/2025 |
Plan Review - Building Approved |
| 2/14/2025 |
Plan Review - Reviewed |
| 2/14/2025 |
Final Review - Processing |
| 2/20/2025 |
Final Review - Payment Needed |
| 2/20/2025 |
Permit Issued |