| Inspection |
Notes |
Performed By |
Date |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
3/6/2025 |
| Release to power company |
|
Matt Forsyth |
3/6/2025 |
| Cancelled: Electrical - Temporary Service |
|
Gary Pitzer |
3/7/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Footing Needs To Be Dried Out Compaction Needed In Footing |
Matt Forsyth |
3/25/2025 |
| Passed: Building - Monolithic Slab |
Finished Floor Elevation Will Be Needed By Nailing Inspection |
Matt Forsyth |
4/9/2025 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
4/9/2025 |
| Cancelled: Building - Footer |
|
Matt Forsyth |
4/9/2025 |
| Cancelled: Engineering - Setbacks |
|
Matt Forsyth |
4/9/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Straps On Posts Needed |
Matt Forsyth |
4/28/2025 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
4/28/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Post Strapping |
Matt Forsyth |
4/29/2025 |
| Passed: Electrical - 2nd Rough-In |
30 Amp Wire Running Outside Needs Staple Within 6 Inches Exiting Wall |
Matt Forsyth |
5/28/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
5/28/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
5/28/2025 |
| Passed: Building - Framing |
|
Matt Forsyth |
5/29/2025 |
| Failed: Building - Insulation |
No Work Done |
Matt Forsyth |
6/4/2025 |
| Passed: Building - Insulation |
The Wall Insulation Is Complete |
Matt Forsyth |
6/6/2025 |
| Passed: Electrical - Permanent Power |
Septic Needed |
Matt Forsyth |
7/31/2025 |
| Release to power company |
|
Ewilliams |
8/1/2025 |
| Septic Release Inspection |
|
Health Dept |
8/1/2025 |
| Passed: Building - Final |
Need Blower Door Test And Final Termite Treatment |
Matt Forsyth |
10/8/2025 |