Permit Details

Permit Search

Permit

Communications Tower

5348 NW US HIGHWAY 41
LAKE CITY, FL 32055

Permit #
000052227
Application #
68889
Status Completed
  1. Submitted Jan 8, 2025
  2. Issued Jan 31, 2025
  3. Expires Jan 7, 2026
  4. Completed Jul 11, 2025

Property

Parcel #
01936-000
Owner
Southern Stone Communications
Acres
2.68
Subdivision
—
Zoning
RR
Flood zone
X
District
1

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0195D
This is the construction of a:
Verizon Wireless collocation of equipment to the tower and ground space of existing 340' guyed tower.
Select access to property:
Existing Drive
Total Estimated Cost
40000.00
Tower Height
340
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Is this a new or existing tower?
Existing
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Plan Review - Corrections Needed
  4. Point Review - Printed-Online Application
  5. Point Review - Reviewed
  6. Zoning Review - Reviewed
  7. Plan Review - Corrections Needed
  8. Plan Review - Corrections Needed
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Building Approved
  12. Plan Review - Reviewed
  13. Final Review - Processing
  14. Final Review - Payment Needed
  15. Permit Issued
  16. Final Review - Complete

Contractors

  • Matthew Snyder

    New Tech Construction Corporation

    License
    SCC131151517
    Title
    Tower Specialty Contractor
    Role
    Contractor

    Employees Workers Comp Expired.

  • Mark Snyder

    New Tech Construction Corp

    License
    EC13011503
    Title
    Cert. Electrical
    Role
    Subcontractor

Inspections

  1. Apr 1, 2025

    Rescheduled 4/1/2025:Building - Slab

    Inspected by Anthony Aslan

  2. Apr 1, 2025

    Passed: Building - Slab

    2 Small Pads For Equipment And Generator

    Inspected by Gary Pitzer

  3. Apr 4, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  4. Jun 2, 2025

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  5. Jun 2, 2025

    Release to power company

    Inspected by Troy Crews

  6. Jun 2, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  7. Jul 11, 2025

    Passed: Building - Final

    Inspected by Troy Crews

  8. Jul 11, 2025

    Cancelled: Building - Footer

    Inspected by Troy Crews

  9. Jul 11, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  10. Jul 11, 2025

    Cancelled: Building - Slab

    Inspected by Troy Crews

  11. Jul 11, 2025

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  12. Jul 11, 2025

    Release to power company

    Ok To Release Power-- 7.11.25 Mg

    Inspected by Troy Crews

  13. Jul 11, 2025

    Passed: Engineering - Zoning Final

    Inspected by Troy Crews

  14. Jul 11, 2025

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.

  15. Jul 11, 2025

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.