Inspection |
Notes |
Performed By |
Date |
Rescheduled 2/24/2025:Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
2/24/2025 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
2/24/2025 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Melissa Garber |
2/25/2025 |
Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
2/25/2025 |
Passed: Building - Monolithic Slab |
Request A Corner Bar Top Of Deep Footings |
Matt Forsyth |
2/28/2025 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
2/28/2025 |
Release to power company |
Re-release To Change From Fpl To Clay |
Emaleigh Williams |
3/17/2025 |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
3/17/2025 |
Release to power company |
|
Matt Forsyth |
3/17/2025 |
Submitted Power Release through FPL Portal |
|
Garber, Melissa |
3/17/2025 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
3/26/2025 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
3/26/2025 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/26/2025 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
4/3/2025 |
Passed: Building - Framing |
|
Matt Forsyth |
4/3/2025 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/22/2025 |
Passed: Mechanical - Rough In |
Fresh Air Installed For Wood Burning Fireplace |
Matt Forsyth |
4/22/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
Gas Lines For Fixtures Have Been Installed |
Matt Forsyth |
4/22/2025 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Water Tested |
Matt Forsyth |
4/22/2025 |
Passed: Building - Insulation |
Wood Burning Fireplace Make Up Air Installed |
Matt Forsyth |
4/30/2025 |
Septic Release Inspection |
|
Health Dept |
5/7/2025 |