Permit Details

Permit Search

Permit

New Residential Construction

255 SW CHERRYWOOD WAY
LAKE CITY, FL 32025

Permit #
000052105
Application #
68396
Status Completed
  1. Submitted Dec 3, 2024
  2. Issued Jan 17, 2025
  3. Expires Jan 17, 2026
  4. Completed Jul 21, 2025

Property

Parcel #
09415-105
Owner
Bundy Caleb Edward,
Acres
6.03
Subdivision
Magnolia Place
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
2' above the highest adjacent natural grade
Fema map number
12023C0415C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2423
Total Area (Sqft)
3995
Building Height
218
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0915
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - On Hold-Incomplete
  5. Point Review - On Hold-Incomplete
  6. Zoning Review - On Hold-Incomplete
  7. Plan Review - On Hold-Incomplete
  8. Point Review - Printed-Online Application
  9. Point Review - Reviewed
  10. Zoning Review - Reviewed
  11. Plan Review - Documents Required
  12. Plan Review - Corrections Needed
  13. Plan Review - Corrections Needed
  14. Plan Review - Corrections Needed
  15. Plan Review - Building Approved
  16. Plan Review - Electrical Approved
  17. Plan Review - Mechanical Approved
  18. Plan Review - Plumbing Approved
  19. Plan Review - Fuel/Gas Approved
  20. Plan Review - Reviewed
  21. Final Review - Documents Required
  22. Final Review - Documents Required
  23. Final Review - Documents Required
  24. Final Review - Payment Needed
  25. Permit Issued
  26. Final Review - Complete
  27. Final Review - Payment Needed
  28. Final Review - Complete

Contractors

  • Brenton M Franklin

    Axis Management Inc.

    License
    CGC1527423
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Nicholas Tyre

    Creative Concepts Home & Landscaping

    License
    CCC1334900
    Title
    Cert. Roofing
    Role
    Subcontractor
  • Donald Davis

    High Springs Electric Inc

    License
    EC0002306
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Donald R Davis

    High Springs Electric Inc

    License
    CAC1815367
    Title
    Class B A/c
    Role
    Subcontractor

Inspections

  1. Jan 21, 2025

    Passed: Building - Footer

    Inspected by Anthony Aslan

  2. Jan 21, 2025

    Passed: Engineering - Setbacks

    Appears Within Setbacks

    Inspected by Anthony Aslan

  3. Feb 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Block On North End Pushed In

    Inspected by Anthony Aslan

  4. Feb 24, 2025

    Passed: Building - Slab

    Electric Pipe Not Capped Off

    Inspected by Anthony Aslan

  5. Feb 26, 2025

    Cancelled: Building - Slab

    Inspected by Anthony Aslan

  6. Mar 13, 2025

    Passed: Building - Strapping

    Strapping For Posts, Windows And Doors On Exterior, Also Has Roof Truss Screws

    Inspected by Gary Pitzer

  7. Mar 13, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  8. Mar 13, 2025

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  9. Mar 13, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Porch Post Exterior Garage Only

    Inspected by Gary Pitzer

  10. Mar 24, 2025

    Passed: Building - Rated Assembly Fastening

    Screws, Widows Or To Seal Framing Ok

    Inspected by Gary Pitzer

  11. Apr 3, 2025

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Anthony Aslan

  12. Apr 3, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  13. Apr 3, 2025

    Passed: Mechanical - Rough In

    Inspected by Anthony Aslan

  14. Apr 3, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  15. Apr 3, 2025

    Passed: Building - Framing

    Inspected by Anthony Aslan

  16. Apr 11, 2025

    Passed: Building - Insulation

    Foam, Walls And Roof

    Inspected by Gary Pitzer

  17. May 15, 2025

    Failed: Electrical - Permanent Power

    Need Outlets Installed And Panel Made Up With Breakers

    Inspected by Anthony Aslan

  18. Jun 3, 2025

    Cancelled: Electrical - Temporary Service

    Inspected by Anthony Aslan

  19. Jun 3, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release(rec'd) & Final Drive (blake Ok'd To Let Go Until Co - 6.13.25 Mg)

    Inspected by Anthony Aslan

  20. Jun 10, 2025

    Septic Release Inspection

    Inspected by Health Dept

  21. Jun 19, 2025

    Release to power company

    Inspected by Melissa Garber

  22. Jul 11, 2025

    Passed: Building - Final

    Need Fresh Pictures, Blower Door Required Prior To Co-- 7.14.25 Mg

    Inspected by Anthony Aslan

  23. Jul 21, 2025

    Passed: Certificate-Release Certificate

    Rec'd Septic & Fresh Pics

    Inspected by Anthony Aslan

Documents