Permit Details

Permit Search

Permit

Roof Replacement or Repair

205 SW THOMPKINS LOOP
LAKE CITY, FL 32025

Permit #
000052043
Application #
68809
Status Completed
  1. Submitted Jan 1, 2025
  2. Issued Jan 13, 2025
  3. Expires Jul 30, 2025
  4. Completed Jan 31, 2025

Property

Parcel #
08640-016
Owner
Goodbread Michael, Goodbread Teresa
Acres
0.72
Subdivision
242 Village
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0401C
Type Roofing Job
Overlay with Metal
Further Job Details (Explain if decking is being replaced and or Repairs are being done.)
1 x 4 furring over exist shingle roof.. 29 Ga. metal
Type of structure
House
Commercial or Residential
Residential
Roof Area (for this job) Sq Ft
1800
No. of Stories
1
Roof Pitch
2:12 to 4:12
Is the existing roof being removed?
No
Explain if not removing the existing roofing material?
1 x 4 furring over shingles ... 29 ga. ultra-rib metal
Type of New Roofing Product
Metal
Florida Product Approval Number
fl-4595.19
Product Manufacturer
Tri county
Product Description
29 ga. ultr-rib
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Sealed roof decking options: (Must select an option.)
Other (explain)
Sealed roof decking explanation for other option.
metal overlay
Ventilation:
Ridge Vent
Flashing:
Replace All
Drip Edge:
Replace All
Valley Treatment:
New Metal
Any cable and/or race-way wiring located on or within the roof assembly?
Yes

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified.
  4. Final Review - Corrections Needed
  5. Final Review - Payment Needed
  6. Permit Issued

Contractors

  • Paul Spicer

    Spicer Construction Inc

    License
    CCC048156
    Title
    Cert Roofing
    Role
    Contractor

Inspections

  1. Jan 15, 2025

    Passed: Re-Roof - In Progress

    In Progress With Metal Over Lay Roof, Furring Stops Being Installed

    Inspected by Gary Pitzer

  2. Jan 24, 2025

    Failed: Re-Roof - Final

    Pictures Required For Final

    Inspected by Troy Crews

  3. Jan 30, 2025

    Cancelled: Re-Roof - Final

    Inspected by Melissa Garber

  4. Jan 31, 2025

    Failed: Re-Roof - In Progress

    If No Pictures Contractor Will Need To Meet Inspector There And Remove A Panel

    Inspected by Troy Crews

  5. Jan 31, 2025

    Passed: Re-Roof - Final

    Inspected by Gary Pitzer