Permit Details

Permit Search

Permit

New Residential Construction

632 SW RIDGE ST
LAKE CITY, FL 32024

Permit #
000052031
Application #
68207
Status Completed
  1. Submitted Nov 20, 2024
  2. Issued Jan 9, 2025
  3. Expires Apr 1, 2026
  4. Completed Oct 3, 2025

Property

Parcel #
03155-118
Owner
Hunter Kyle, Hunter Markie
Acres
4.10
Subdivision
Oak Ridge Estates Unit Iii
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0381D
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2456
Total Area (Sqft)
3801
Building Height
21
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0733
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Point Review - Reviewed
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Plumbing Approved
  9. Plan Review - Mechanical Approved
  10. Plan Review - Electrical Approved
  11. Plan Review - Building Approved
  12. Plan Review - Reviewed
  13. Final Review - Processing
  14. Final Review - Payment Needed
  15. Final Review - Payment Needed
  16. Final Review - Payment Needed
  17. Final Review - Payment Needed
  18. Permit Issued
  19. Final Review - Complete

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Robert Ogles

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Jan 21, 2025

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  2. Jan 21, 2025

    Passed: Building - Footer

    2 # 5 Rebar Wired And On Chairs, Electrical Rebar Bond

    Inspected by Gary Pitzer

  3. Feb 4, 2025

    Passed: Electrical - Temporary Service

    Inspected by Gary Pitzer

  4. Feb 4, 2025

    Release to power company

    Inspected by Gary Pitzer

  5. Mar 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv Only With Clean Out On Exterior,no Water Or Gas

    Inspected by Gary Pitzer

  6. Mar 17, 2025

    Passed: Electrical - 1st Underground Rough–In

    Underxlab Conduits And Floor Box

    Inspected by Gary Pitzer

  7. Mar 31, 2025

    Passed: Building - Slab

    Inspected by Gary Pitzer

  8. May 22, 2025

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  9. May 22, 2025

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  10. Jun 11, 2025

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Gary Pitzer

  11. Jun 11, 2025

    Passed: Building - Framing

    Inspected by Gary Pitzer

  12. Jun 11, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  13. Jun 11, 2025

    Failed: Mechanical - Rough In

    Duct Not Complete, Vents From Bath Fans Not Complete

    Inspected by Gary Pitzer

  14. Jun 11, 2025

    Failed: Electrical - 2nd Rough-In

    In Progress With Installation

    Inspected by Gary Pitzer

  15. Jun 16, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  16. Jun 16, 2025

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  17. Jun 25, 2025

    Passed: Building - Insulation

    Foam Walls And Roof

    Inspected by Gary Pitzer

  18. Aug 13, 2025

    Passed: Electrical - Permanent Power

    Need Septoc Release

    Inspected by Anthony Aslan

  19. Aug 19, 2025

    Release to power company

    Rec'd Septic Final

    Inspected by Ewilliams

  20. Aug 19, 2025

    Septic Release Inspection

    Inspected by Health Dept

  21. Sep 29, 2025

    Failed: Building - Final

    Needs Drive Apron Completed And Passed

    Inspected by Gary Pitzer

  22. Oct 3, 2025

    Passed: Building - Final

    All Requirements Met To Release Co-- 10.3.25 Mg

    Inspected by Gary Pitzer

Documents