Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas-1st Underground Rough–In |
Underground Rough Plumbing Passed By Ashley Holcombe |
Private Provider |
1/21/2025 |
Passed: Building-Footer |
Footer Passed By Seth Green |
Private Provider |
1/28/2025 |
Passed: Building-Slab |
Structural Slab Inspection Passed By Seth Green |
Private Provider |
1/28/2025 |
Passed: Electrical -2nd Rough-In |
Concrete Encased Electrodes Passed By Seth Green |
Private Provider |
1/28/2025 |
Building-Roof Decking |
Roof Sheathing Passed By Ashley Holcombe |
Private Provider |
2/11/2025 |
Building-Wall Sheathing |
Wall Sheathing Passed By Ashley Holcombe |
Private Provider |
2/11/2025 |
Building-Ext Strapping/Wall Sheathing |
Roof Flashing Passed By Ashely Holcombe |
Private Provider |
2/25/2025 |
Electrical -1st Underground Rough–In |
Electrical Rough Passed By Ashley Holcombe |
Private Provider |
2/28/2025 |
Mechanical-Rough In |
Mechanical Rough Passed By Ashley Holcombe |
Private Provider |
2/28/2025 |
Plumbing/Gas-1st Underground Rough–In |
Plumbing Rough/top Out Passed By Ashley Holcombe |
Private Provider |
2/28/2025 |
Building-Ext Strapping/Wall Sheathing |
Window And Door Attachment Passed By Ashley Holcombe |
Private Provider |
2/28/2025 |
Building-Strapping |
Housewrap Passed By Ashley Holcombe
|
Private Provider |
2/28/2025 |
Passed: Building-Framing |
Framing Passed By Ashley Holcombe |
Private Provider |
2/28/2025 |
Building-Insulation |
Insulation Passed By Ashley Holcombe |
Private Provider |
3/6/2025 |
Electrical -Permanent Power |
Semi-perm Passed By Seth Green |
Private Provider |
4/14/2025 |
Release to power company |
|
Private Provider |
5/5/2025 |
Submitted Power Release through FPL Portal |
|
Garber, Melissa |
5/5/2025 |
Passed: Mechanical-Rough In |
Mechanical Final Passed By Seth Green |
Private Provider |
7/14/2025 |
Passed: Electrical -Permanent Power |
Electrical Final Passed By Seth Green |
Private Provider |
7/14/2025 |
Passed: Plumbing/Gas-2nd Rough-In |
Plumbing Final Passed By Seth Green |
Private Provider |
7/14/2025 |
Passed: Building-Final |
Building Final Passed By Seth Green |
Private Provider |
7/14/2025 |
Passed: Certificate-Release Certificate |
Cert Of Compliance Rec'd 7.15.25 |
Private Provider |
7/16/2025 |