Permit Details

Permit Search

Permit

New Commercial Construction

2102 SE BAYA DR
LAKE CITY, FL 32025

Permit #
000052003
Application #
67653
Status Completed
  1. Submitted Nov 5, 2024
  2. Issued Jan 7, 2025
  3. Expires Jan 7, 2026
  4. Completed Jul 11, 2025

Property

Parcel #
06970-004
Owner
Oasis Oaks, Inc, (coopers Hideout)
Acres
2.03
Subdivision
—
Zoning
CI
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0311D
This is the construction of a:
Recreation Facility
Driveway access to property:
D.O.T. Permit
Is there a Fire Sprinkler System?
No
Setbacks Front
20'
Setback Side 1
0'
Setback Side 2
0'
Setback Rear
15'
Describe commercial use:
Recreation Facility
Stories
1
Heated Area (Sqft)
0
Total Area (Sqft)
7920
Building Height
31
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Utility & Misc
Dev Permit #
F023-
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0824
Sealed roof decking options. (Must select one.)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Sealed roof decking explanation for other option.
Pole barn
Service Amps
400

Status & Review History

  1. Application pending.
  2. City of Lake City Utilities Notified.
  3. Application submitted by applicant.
  4. City of Lake City Utilities Notified.
  5. Point Review - Printed-Online Application
  6. Zoning Review - Reviewed
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Building Approved
  10. Plan Review - Reviewed
  11. Final Review - Processing
  12. Final Review - Documents Required
  13. Final Review - Documents Required
  14. Final Review - Documents Required
  15. Final Review - Documents Required
  16. Final Review - Processing
  17. Final Review - Payment Needed
  18. Permit Issued

Contractors

  • Ronnie Edenfield

    Scci Inc

    License
    CBC1267457
    Title
    Cert. Building
    Role
    Contractor
  • Don C Bills Sr

    Hometown Plumbing Services Llc

    License
    CFC1428890
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Donald Davis

    High Springs Electric Inc

    License
    EC0002306
    Title
    Electrical Contractor
    Role
    Subcontractor

Inspections

  1. Jan 21, 2025

    Cancelled: Building - Footer

    Inspected by Melissa Garber

  2. Jan 21, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Melissa Garber

  3. Jan 21, 2025

    Cancelled: Electrical - Temporary Service

    Inspected by Melissa Garber

  4. Jan 21, 2025

    Passed: Building - Footer

    Inspected by Troy Crews

  5. Jan 21, 2025

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  6. Jan 21, 2025

    Passed: Electrical - Temporary Service

    Inspected by Troy Crews

  7. Jan 21, 2025

    Release to power company

    Inspected by Troy Crews

  8. Feb 17, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv Pipe Underslab Only

    Inspected by Matt Forsyth

  9. Feb 25, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  10. Apr 11, 2025

    Passed: Electrical - Permanent Power

    Need Final From Dot On Driveway Prior To Release

    Inspected by Troy Crews

  11. May 13, 2025

    Release to power company

    Dot Final Recieved-- Need Final Septic Prior To Release Of Power 6.15.25 Mg

    Inspected by Troy Crews

  12. May 13, 2025

    Passed: Engineering - D.O.T Final Driveway

    Inspected by Brad Long

  13. Jul 1, 2025

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City's Distribution & Collections Department

  14. Jul 1, 2025

    Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection

    Inspected by City Of Lake City's Distribution & Collections Department

  15. Jul 2, 2025

    Passed: Building - Final

    *power Release And Co Pending Septic Final And Fire Final-- 7.2.25 Mg

    Inspected by Troy Crews

  16. Jul 2, 2025

    Rescheduled 7/3/2025:Fire - Fire Final

    Inspected by Melissa Garber

  17. Jul 3, 2025

    Passed: Fire - Fire Final

    Inspected by Cpt. Shane Overstreet

  18. Jul 11, 2025

    Release to power company

    Rec'd Septic Final 7/11

    Inspected by Ewilliams

  19. Jul 11, 2025

    Passed: Certificate-Release Certificate

    Rec'd Septic Final And Fire Final

    Inspected by Emaleigh Williams

  20. Jul 11, 2025

    Submitted Power Release through FPL Portal

    Inspected by Ward, Emaleigh C.

  21. Jul 12, 2025

    Submitted Power Release through FPL Portal

    Inspected by Garber, Melissa

  22. Jul 16, 2025

    Septic Release Inspection

    Inspected by Health Dept

Documents