Permit Details

Permit Search

Permit

New Residential Construction

256 NW LEVI GLN
LAKE CITY, FL 32055

Permit #
000052000
Application #
68304
Status Completed
  1. Submitted Nov 23, 2024
  2. Issued Jan 6, 2025
  3. Expires Feb 21, 2026
  4. Completed Aug 25, 2025

Property

Parcel #
02032-211
Owner
Park James, Park Rhonda
Acres
4.98
Subdivision
Hills Of Huntsville Phase 2
Zoning
A-3
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the Paved road
Fema map number
12023C0280D
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2000
Total Area (Sqft)
3021
Building Height
8
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0837
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Reviewed
  4. Point Review - Printed-Online Application
  5. Zoning Review - Reviewed
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Plumbing Approved
  11. Plan Review - Mechanical Approved
  12. Plan Review - Electrical Approved
  13. Plan Review - Building Approved
  14. Plan Review - Reviewed
  15. Final Review - Processing
  16. Final Review - Reviewed
  17. Final Review - Payment Needed
  18. Final Review - Payment Needed
  19. Permit Issued
  20. Final Review - Complete

Contractors

  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CGC1516042
    Title
    General Contractor
    Role
    Contractor
  • Roger Whiddon

    Lake City Plumbing Inc

    License
    CFC1428686
    Title
    Cert Plumbing
    Role
    Subcontractor
  • Kevin L Bedenbaugh Jr

    Plumb Level Construction Co Llc

    License
    CCC1329482
    Title
    Roofing Contractor
    Role
    Subcontractor
  • Donald Davis

    High Springs Electric Inc

    License
    EC0002306
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Richard M Touchstone

    Touchstone Heating & Air Inc

    License
    CAC058099
    Title
    Class B A/c Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jan 8, 2025

    Passed: Building - Footer

    Inspected by Troy Crews

  2. Jan 8, 2025

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 24, 2025

    Passed: Electrical - Temporary Service

    Inspected by Matt Forsyth

  4. Jan 24, 2025

    Release to power company

    Inspected by Matt Forsyth

  5. Jan 29, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv And Cpvc Water Lines, 125 Psi On Test

    Inspected by Gary Pitzer

  6. Feb 11, 2025

    Failed: Building - Slab

    Request Pictures Of Hook Bar With Clean Out That Were Filled With Dirt

    Inspected by Matt Forsyth

  7. Feb 14, 2025

    Passed: Building - Slab

    Block Cells Cleaned Out

    Inspected by Matt Forsyth

  8. Mar 12, 2025

    Passed: Building - Ext Strapping/Wall Sheathing

    Some Post Bottom Plates Fasteners Need To Be Finished

    Inspected by Matt Forsyth

  9. Mar 12, 2025

    Passed: Building - Framing

    Truss Engineering Inspected With Interior And Exterior Walls

    Inspected by Matt Forsyth

  10. Mar 12, 2025

    Passed: Building - Roof Decking

    Inspected by Matt Forsyth

  11. Mar 12, 2025

    Passed: Building - Wall Sheathing

    Permit Is Missing At The Box

    Inspected by Matt Forsyth

  12. Apr 3, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Matt Forsyth

  13. Apr 3, 2025

    Passed: Mechanical - Rough In

    Inspected by Matt Forsyth

  14. Apr 3, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Matt Forsyth

  15. Apr 3, 2025

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Matt Forsyth

  16. Apr 28, 2025

    Passed: Building - Insulation

    Foam

    Inspected by Matt Forsyth

  17. Jun 27, 2025

    Septic Release Inspection

    Inspected by Health Dept

  18. Jun 30, 2025

    Passed: Electrical - Permanent Power

    Meter Can Installed Ready For Permanent Power

    Inspected by Matt Forsyth

  19. Jun 30, 2025

    Release to power company

    Inspected by Matt Forsyth

  20. Jul 2, 2025

    Release to power company

    Re-release

    Inspected by Matt Forsyth

  21. Aug 22, 2025

    Failed: Building - Final

    Need Final Termite Treatment Picture Of Ventilation Fans Termination Point

    Inspected by Matt Forsyth

  22. Aug 25, 2025

    Passed: Certificate-Release Certificate

    Inspected by Matt Forsyth

  23. Aug 25, 2025

    Passed: Building - Final

    Items Were Addressed - All Requirements Met To Release Co-- 8.25.25 Mg

    Inspected by Matt Forsyth

Documents