| Inspection |
Notes |
Performed By |
Date |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
12/20/2024 |
| Release to power company |
|
Matt Forsyth |
12/20/2024 |
| Failed: Building - Footer |
Gate Locked. |
Troy Crews |
1/6/2025 |
| Failed: Engineering - Setbacks |
|
Troy Crews |
1/6/2025 |
| Passed: Building - Footer |
|
Troy Crews |
1/6/2025 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
1/6/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Dwv Only |
Matt Forsyth |
2/14/2025 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
2/18/2025 |
| Cancelled: Building - Footer |
|
Emaleigh Williams |
2/25/2025 |
| Cancelled: Engineering - Setbacks |
|
Emaleigh Williams |
2/25/2025 |
| Cancelled: Building - Footer |
|
Emaleigh Williams |
2/25/2025 |
| Cancelled: Engineering - Setbacks |
|
Emaleigh Williams |
2/25/2025 |
| Cancelled: Building - Footer |
|
Emaleigh Williams |
2/25/2025 |
| Cancelled: Engineering - Setbacks |
|
Emaleigh Williams |
2/25/2025 |
| Passed: Building - Slab |
|
Troy Crews |
2/26/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Proper Nails Are Screws Need To Be Used On Base Plates Of Post |
Matt Forsyth |
3/13/2025 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
3/13/2025 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/13/2025 |
| Passed: Building - Framing |
Partial Framing |
Matt Forsyth |
3/18/2025 |
| Cancelled: Building - Rated Assembly Fastening |
|
Matt Forsyth |
3/18/2025 |
| Passed: Building - Strapping |
|
Matt Forsyth |
3/18/2025 |
| Passed: Building - Framing |
|
Matt Forsyth |
4/22/2025 |
| Passed: Building - Rated Assembly Fastening |
Commercial Attachment For Windows And Doors |
Matt Forsyth |
4/22/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/22/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/22/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Behind Wall Supply For Gas |
Matt Forsyth |
4/22/2025 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tubs Have Been Water Tested |
Matt Forsyth |
4/22/2025 |
| Passed: Building - Insulation |
|
Matt Forsyth |
4/29/2025 |
| Septic Release Inspection |
|
Health Dept |
5/16/2025 |
| Release to power company |
Ok To Release Power-- 9.16.25 Mg |
Ewilliams |
9/16/2025 |
| Release to power company |
Ok To Release Power-- 9.16.25 Mg |
Ewilliams |
9/16/2025 |
| Passed: Electrical - Permanent Power |
Ok To Release Power-- 9.16.25 Mg |
Matt Forsyth |
9/16/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
9/16/2025 |
| Passed: Building - Final |
All Requirements Met To Release Co-- 9.17.25 Mg |
Matt Forsyth |
9/17/2025 |
| (Requested) Engineering-As-Built Survey Review |
|
|
|