Inspection |
Notes |
Performed By |
Date |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
1/27/2025 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
1/30/2025 |
Passed: Engineering - Setbacks |
|
Troy Crews |
1/30/2025 |
Passed: Building - Roof Decking |
|
Troy Crews |
3/10/2025 |
Passed: Building - Wall Sheathing |
|
Troy Crews |
3/10/2025 |
Passed: Building - Framing |
|
Troy Crews |
3/21/2025 |
Passed: Electrical - 2nd Rough-In |
Electrician To Check Out Outlet Box In Rear Bathroom |
Troy Crews |
3/21/2025 |
Passed: Mechanical - Rough In |
|
Troy Crews |
3/21/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
3/21/2025 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
3/21/2025 |
Cancelled: Building - Framing |
|
Troy Crews |
3/31/2025 |
Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
3/31/2025 |
Cancelled: Mechanical - Rough In |
|
Troy Crews |
3/31/2025 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
3/31/2025 |
Cancelled: Plumbing/Gas - Tub Set/Shower Pan |
|
Troy Crews |
3/31/2025 |
Passed: Building - Insulation |
|
Troy Crews |
4/2/2025 |
Passed: Electrical - Permanent Power |
|
Troy Crews |
4/25/2025 |
Release to power company |
Drive Final Required Prior To Release Of Power To Fpl (rec'd) |
Troy Crews |
4/25/2025 |
Submitted Power Release through FPL Portal |
|
Garber, Melissa |
5/5/2025 |
Passed: City of Lake City Utilities - Lake City Utilities Tap Inspection |
|
City Of Lake City Distribution And Collections Department |
5/23/2025 |
Passed: Certificate-Release Certificate |
|
Troy Crews |
6/20/2025 |
Passed: Building - Final |
Ok To Release Co-- 6.20.25 Mg |
Troy Crews |
6/20/2025 |