Permit Details

Permit Search

Permit

New Residential Construction

5801 SE COUNTRY CLUB RD
LAKE CITY, FL 32025

Permit #
000051776
Application #
67366
Status Completed
  1. Submitted Oct 4, 2024
  2. Issued Dec 11, 2024
  3. Expires Mar 17, 2026
  4. Completed Sep 23, 2025

Property

Parcel #
08769-003
Owner
Bootle Victoria, Bootle Heath
Acres
7.32
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0401C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
2
Heated Area (Sqft)
2328
Total Area (Sqft)
3425
Building Height
25
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0814
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Zoning Review - Documents Required
  5. Zoning Review - Documents Required
  6. Zoning Review - Reviewed
  7. Plan Review - Corrections Needed
  8. Plan Review - Corrections Needed
  9. Plan Review - On Hold-Incomplete
  10. Plan Review - On Hold-Incomplete
  11. Plan Review - Documents Required
  12. Plan Review - Documents Required
  13. Plan Review - Plumbing Approved
  14. Plan Review - Mechanical Approved
  15. Plan Review - Electrical Approved
  16. Plan Review - Building Approved
  17. Final Review - Processing
  18. Final Review - Payment Needed
  19. Final Review - Payment Needed
  20. Permit Issued
  21. Final Review - Payment Needed
  22. Final Review - Complete

Contractors

  • Dustin Busscher

    Busscher Enterprises Llc Dba Jbc Builders

    License
    CBC1263910
    Title
    Cert. Building
    Role
    Contractor
  • Alaina Perry

    North Florida Maintenance And Repair Services Llc

    License
    ER13016315
    Title
    Reg. Electrical
    Role
    Subcontractor

    County License & State License Expired.

  • Robert Jarvis

    Jarvis Heat And Air Llc

    License
    CAC1816766
    Title
    Class "b" A/c
    Role
    Subcontractor

    County License & State License Expired.

  • Roger Whiddon

    Lake City Plumbing Inc

    License
    CFC1428686
    Title
    Cert Plumbing
    Role
    Subcontractor
  • Nicholas Tyre

    Creative Concepts Home & Landscaping

    License
    CCC1334900
    Title
    Cert. Roofing
    Role
    Subcontractor

Inspections

  1. Dec 31, 2024

    Passed: Electrical - Temporary Service

    Need Blank Off Cover On Empty Spaces Of Panel

    Inspected by Anthony Aslan

  2. Jan 10, 2025

    Passed: Building - Footer

    Inspected by Anthony Aslan

  3. Jan 10, 2025

    Passed: Engineering - Setbacks

    Appears Within Setbacks

    Inspected by Anthony Aslan

  4. Jan 23, 2025

    Passed: Electrical - Temporary Service

    Blank Off Installed

    Inspected by Anthony Aslan

  5. Jan 23, 2025

    Release to power company

    Inspected by Anthony Aslan

  6. Jan 31, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  7. Feb 3, 2025

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Dwv And Water Lines 100psi On Water

    Inspected by Gary Pitzer

  8. Feb 4, 2025

    Rescheduled 2/4/2025:Building - Slab

    Inspected by Troy Crews

  9. Feb 4, 2025

    Passed: Building - Slab

    Plastic, Steel And Wire

    Inspected by Gary Pitzer

  10. Mar 3, 2025

    Failed: Building - Roof Decking

    Not Ready

    Inspected by Anthony Aslan

  11. Mar 3, 2025

    Passed: Building - Wall Sheathing

    Inspected by Anthony Aslan

  12. Mar 7, 2025

    Passed: Building - Roof Decking

    Partial Roof porch Not Complete, Gables Not Complete Main Body

    Inspected by Anthony Aslan

  13. Mar 18, 2025

    Passed: Building - Framing

    Window Screws Only Not Full Framing

    Inspected by Troy Crews

  14. Mar 18, 2025

    Passed: Building - Roof Decking

    Inspected by Troy Crews

  15. Mar 27, 2025

    Cancelled: Building - Framing

    Inspected by Emaleigh Williams

  16. Mar 27, 2025

    Cancelled: Building - Strapping

    Inspected by Emaleigh Williams

  17. Mar 27, 2025

    Cancelled: Electrical - 2nd Rough-In

    Inspected by Emaleigh Williams

  18. Mar 27, 2025

    Cancelled: Mechanical - Rough In

    Inspected by Emaleigh Williams

  19. Mar 27, 2025

    Cancelled: Plumbing/Gas - 2nd Rough-In

    Inspected by Emaleigh Williams

  20. Mar 28, 2025

    Cancelled: Building - Framing

    Inspected by Emaleigh Williams

  21. Mar 28, 2025

    Cancelled: Building - Strapping

    Inspected by Emaleigh Williams

  22. Mar 28, 2025

    Cancelled: Electrical - 2nd Rough-In

    Inspected by Emaleigh Williams

  23. Mar 28, 2025

    Cancelled: Mechanical - Rough In

    Inspected by Emaleigh Williams

  24. Mar 28, 2025

    Cancelled: Plumbing/Gas - 2nd Rough-In

    Inspected by Emaleigh Williams

  25. Apr 4, 2025

    Passed: Building - Framing

    Inspected by Anthony Aslan

  26. Apr 4, 2025

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Anthony Aslan

  27. Apr 4, 2025

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  28. Apr 4, 2025

    Failed: Mechanical - Rough In

    All Exhaust Fans Not Sealed At Fan strapping Missing On Some Of Flex Duct drain Line On Upstairs Needs Insulation In Attic Section

    Inspected by Anthony Aslan

  29. Apr 9, 2025

    Passed: Mechanical - Rough In

    Inspected by Anthony Aslan

  30. Apr 17, 2025

    Cancelled: Building - Insulation

    Inspected by Emaleigh Williams

  31. Apr 21, 2025

    Passed: Building - Insulation

    Spray Foam Bonus And Attic walls Batt

    Inspected by Anthony Aslan

  32. Jun 20, 2025

    Cancelled: Electrical - Permanent Power

    Inspected by Anthony Aslan

  33. Jun 20, 2025

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  34. Jul 2, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Anthony Aslan

  35. Jul 21, 2025

    Release to power company

    Rec'd Septic 7/21/25

    Inspected by Ewilliams

  36. Jul 30, 2025

    Septic Release Inspection

    Inspected by Health Dept

  37. Sep 11, 2025

    Cancelled: Engineering - D.O.T Final Driveway

    Not A Sr Access.

    Inspected by Brad Long

  38. Sep 18, 2025

    Passed: Building - Final

    Inspector Ok'd Pics - 9.23.25 Mg

    Inspected by Anthony Aslan