Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
Need Blank Off Cover On Empty Spaces Of Panel |
Anthony Aslan |
12/31/2024 |
Passed: Building - Footer |
|
Anthony Aslan |
1/10/2025 |
Passed: Engineering - Setbacks |
Appears Within Setbacks |
Anthony Aslan |
1/10/2025 |
Passed: Electrical - Temporary Service |
Blank Off Installed |
Anthony Aslan |
1/23/2025 |
Release to power company |
|
Anthony Aslan |
1/23/2025 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
1/31/2025 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Dwv And Water Lines 100psi On Water |
Gary Pitzer |
2/3/2025 |
Rescheduled 2/4/2025:Building - Slab |
|
Troy Crews |
2/4/2025 |
Passed: Building - Slab |
Plastic, Steel And Wire |
Gary Pitzer |
2/4/2025 |
Failed: Building - Roof Decking |
Not Ready |
Anthony Aslan |
3/3/2025 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
3/3/2025 |
Passed: Building - Roof Decking |
Partial Roof
porch Not Complete, Gables Not Complete Main Body |
Anthony Aslan |
3/7/2025 |
Passed: Building - Framing |
Window Screws Only Not Full Framing |
Troy Crews |
3/18/2025 |
Passed: Building - Roof Decking |
|
Troy Crews |
3/18/2025 |
Cancelled: Building - Framing |
|
Emaleigh Williams |
3/27/2025 |
Cancelled: Building - Strapping |
|
Emaleigh Williams |
3/27/2025 |
Cancelled: Electrical - 2nd Rough-In |
|
Emaleigh Williams |
3/27/2025 |
Cancelled: Mechanical - Rough In |
|
Emaleigh Williams |
3/27/2025 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Emaleigh Williams |
3/27/2025 |
Cancelled: Building - Framing |
|
Emaleigh Williams |
3/28/2025 |
Cancelled: Building - Strapping |
|
Emaleigh Williams |
3/28/2025 |
Cancelled: Electrical - 2nd Rough-In |
|
Emaleigh Williams |
3/28/2025 |
Cancelled: Mechanical - Rough In |
|
Emaleigh Williams |
3/28/2025 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Emaleigh Williams |
3/28/2025 |
Passed: Building - Framing |
|
Anthony Aslan |
4/4/2025 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
4/4/2025 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/4/2025 |
Failed: Mechanical - Rough In |
All Exhaust Fans Not Sealed At Fan
strapping Missing On Some Of Flex Duct
drain Line On Upstairs Needs Insulation In Attic Section |
Anthony Aslan |
4/4/2025 |
Passed: Mechanical - Rough In |
|
Anthony Aslan |
4/9/2025 |
Cancelled: Building - Insulation |
|
Emaleigh Williams |
4/17/2025 |
Passed: Building - Insulation |
Spray Foam Bonus And Attic
walls Batt |
Anthony Aslan |
4/21/2025 |