Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Communications Tower Permit
Address 120 SE COMMUNITY DR
LULU, FL 32061
Parcel #: 10491-001
Acres: 3.80
Owner: Cox Donald W, Cox Michelle L
Subdivision:
Zoning: A-3
Flood Zone: X
District: 4
Application #: 68081
Permit #: 000051754
Related Permit:
Submitted: Tuesday, November 12, 2024
Issued: Monday, December 9, 2024
Expires: Wednesday, September 10, 2025
Completed:
Status: Permit Issued
Septic Release? na
Notes:
EXISTING TOWER CO LOCATION
Job Details
Is this a new or existing tower? Existing
Total Estimated Cost 75500.00
Tower Height 190
Select access to property: Existing Drive
Service Amps 200
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Fema map number 12023C0410C
Review Notes
11/12/2024 Application pending.
11/12/2024 Application submitted by applicant.
11/14/2024 Point Review - Printed-Online Application NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/20/2024 Zoning Review - Reviewed NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/20/2024 Plan Review - Electrical Approved NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/20/2024 Plan Review - Building Approved NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/20/2024 Plan Review - Reviewed NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/20/2024 Final Review - Documents Required NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
11/25/2024 Final Review - Documents Required NEEDED * AUTHORIZATION FOR ZACHARY SELF TO ACT AS AGENT * OWNER AND CONTRACTOR SIGNATURE PAGE IS MISSING OWNER SIGNATURE PAGE * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER * LEASEE AGREEMENT * SIGNED SUB FORM FOR ELECTRICAL
12/9/2024 Final Review - Documents Required NEEDED * WE WILL NEED PAPERWORK SHOWING WHO HAS THE AUTHORITY TO SIGN AS THE OWNER-- AUTHORIZATION NEEDED FOR ALYSSA HOULIHAN TO SIGN ON BEHALF OF SBA TOWERS
12/9/2024 Final Review - Reviewed
12/9/2024 Final Review - Payment Needed
12/9/2024 Permit Issued Permit # created and approved from payment.
Contractors
Name/ Business License Title Role
Stanley Maclin
Mastec Network Solutions Llc
CGC1515769 Cert General Contractor
Bradley F Conn
Mastec Network Solutions, Llc
EC13006418 Cert. Electrical Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Electrical - 1st Underground Rough–In Troy Crews 3/7/2025
Passed: Building - Slab Troy Crews 3/7/2025
Passed: Electrical - Permanent Power Troy Crews 3/14/2025
Release to power company Troy Crews 3/14/2025