| Inspection |
Notes |
Performed By |
Date |
| Failed: Plumbing/Gas - 1st Underground Rough–In |
Test Stack Needs To Be On The Highest Fixture Nothing But Air On The High End Of Waste Pipe |
Matt Forsyth |
1/6/2025 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Need Compaction Test For Slab Placement |
Matt Forsyth |
1/7/2025 |
| Passed: Building - Slab |
Fiber Mesh Concrete |
Matt Forsyth |
1/9/2025 |
| Cancelled: Building - Roof Decking |
|
Matt Forsyth |
1/23/2025 |
| Cancelled: Building - Strapping |
|
Matt Forsyth |
1/23/2025 |
| Cancelled: Building - Wall Sheathing |
|
Matt Forsyth |
1/23/2025 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
1/29/2025 |
| Passed: Building - Strapping |
|
Gary Pitzer |
1/29/2025 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
1/29/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
2/19/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
2/19/2025 |
| Failed: Mechanical - Rough In |
Duck Work Thru Ceiling Needs Three Inch Clearance From Framing Members |
Matt Forsyth |
2/19/2025 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
2/19/2025 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
2/19/2025 |
| Failed: Building - Framing |
Attic Access Not Found |
Matt Forsyth |
2/19/2025 |
| Passed: Building - Insulation |
|
Matt Forsyth |
2/24/2025 |
| Passed: Building - Framing |
|
Matt Forsyth |
2/24/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
2/24/2025 |
| Failed: Electrical - Permanent Power |
Not Finished At Metercan Need Septic Release |
Matt Forsyth |
4/23/2025 |
| Passed: Electrical - Permanent Power |
Septic(rec'd) And Drive Final Needed Prior To Release Of Power-- 6.6.25 Mg |
Matt Forsyth |
5/2/2025 |
| Septic Release Inspection |
|
Health Dept |
6/9/2025 |
| Release to power company |
Rec'd Septic And Drive Final |
Emaleigh Williams |
6/18/2025 |
| Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
8/12/2025 |
| Cancelled: Engineering - As-Built Survey Review |
|
Melissa Garber |
8/18/2025 |
| Passed: Electrical - Permanent Power |
Power Already On, Need To Secure Erosion On South Side And Rear Of Home Prior To Final |
Troy Crews |
8/26/2025 |
| Failed: Building - Final |
House Locked |
Troy Crews |
9/8/2025 |
| Failed: Building - Final |
Termite Treatment |
Matt Forsyth |
9/9/2025 |
| Passed: Certificate-Release Certificate |
|
Forsyth, Matthew C. |
9/24/2025 |
| Passed: Building - Final |
Termite Treatmentfinal Inspection Complete. Permit Under Office Review For Co Eligibility. |
Matt Forsyth |
9/24/2025 |