8/27/2024
|
Application pending.
|
8/27/2024
|
Application submitted by applicant.
|
8/27/2024
|
City of Lake City Utilities Notified.
City of Lake City Notified of Application within Utility Service Areas LC_GAS, LC_WATER, LC_SEWER.
|
8/28/2024
|
Point Review - On Hold-Incomplete
NEEDED
* CONTRACTOR'S NAME AND LICENSE # TO BE INPUT IN THE CONTRACTOR SECTION
* SUBCONTRACTORS TO BE LISTED IN CONTRACTOR SECTION
* PRINTED NAME OF WHO SIGNED AS OWNER ON OWNER AND CONTRACTOR SIGNATURE PAGE
* SEALED BUILDING PLANS -
****APPLICATION IS MISSING SEVERAL OTHER DOCS - INCOMPLETE*****
|
9/13/2024
|
Point Review - On Hold-Incomplete
NEEDED
* CONTRACTOR'S NAME AND LICENSE # TO BE INPUT IN THE CONTRACTOR SECTION
* SUBCONTRACTORS TO BE LISTED IN CONTRACTOR SECTION
* PRINTED NAME OF WHO SIGNED AS OWNER ON OWNER AND CONTRACTOR SIGNATURE PAGE
* SEALED BUILDING PLANS -
****APPLICATION IS MISSING SEVERAL OTHER DOCS - INCOMPLETE*****
|
9/20/2024
|
Point Review - Printed-Online Application
NEEDED:
*ADAMS & REYNOLDS UPDATED LICENSE, LIABILITY AND WORKERS COMP
*OWNER AND CONTRACTOR SIGNATURE NAME-- SIGNOR TO SIGN AS WILLIAM ADAMS
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
9/20/2024
|
Point Review - Reviewed
NEEDED:
*ADAMS & REYNOLDS UPDATED LICENSE, LIABILITY AND WORKERS COMP
*OWNER AND CONTRACTOR SIGNATURE NAME-- SIGNOR TO SIGN AS WILLIAM ADAMS
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
9/20/2024
|
Zoning Review - Reviewed
NEEDED:
*ADAMS & REYNOLDS UPDATED LICENSE, LIABILITY AND WORKERS COMP
*OWNER AND CONTRACTOR SIGNATURE NAME-- SIGNOR TO SIGN AS WILLIAM ADAMS
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
9/20/2024
|
Plan Review - On Hold-Incomplete
NEEDED:
*ADAMS & REYNOLDS UPDATED LICENSE, LIABILITY AND WORKERS COMP
*OWNER AND CONTRACTOR SIGNATURE NAME-- SIGNOR TO SIGN AS WILLIAM ADAMS
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
9/30/2024
|
Plan Review - Corrections Needed
NEEDED:
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*PRODUCT APPROVAL CODES
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
9/30/2024
|
Plan Review - Corrections Needed
NEEDED:
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*PRODUCT APPROVAL CODES
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
10/7/2024
|
Plan Review - Documents Required
NEEDED:
*RESIDENTIAL CHECKLIST
*ESTIMATED COST OF CONSTRUCTION
*HEATED/TOTAL AREA CELLS COMPLETED
*ROOF OPTION SELECTED
*911 ADDRESS VERIFICATION
*CITY AVAILABILITY LETTER
*MANUAL J & ENERGY CODE
*SEALED PLANS HAS INVALID SIGNATURE
*PRODUCT APPROVAL CODES
*COMPLETE APPLICANT ADDRESS
*ARCHITECT/ENGINEER CELL NAME, ADDRESS, AND PHONE NUMBER IN CORRESPONDING CELL
*CONTRACTOR AUTHORIZATION FOR NICK APARO
|
10/21/2024
|
Plan Review - Documents Required
NEEDED:
911 ADDRESS VERIFICATION
*SEALED PLANS HAS INVALID SIGNATURE
|
10/25/2024
|
Plan Review - Plumbing Approved
NEEDED:
|
10/25/2024
|
Plan Review - Mechanical Approved
NEEDED:
|
10/25/2024
|
Plan Review - Electrical Approved
NEEDED:
|
10/25/2024
|
Plan Review - Building Approved
NEEDED:
|
10/25/2024
|
Plan Review - Reviewed
NEEDED:
|
10/25/2024
|
Final Review - Processing
NEEDED:
|
10/31/2024
|
Final Review - Corrections Needed
NEEDED:
*DRIVEWAY APPROVAL-- PENDING PAYMENT
|
10/31/2024
|
Final Review - Corrections Needed
NEEDED:
*DRIVEWAY APPROVAL-- PENDING PAYMENT
* FLOODPLAIN ORDINANCE NOTICE TO OWNER - THIS FORM CAN BE FOUND ON THE WEBSITE UNDER THE DOCUMENTS TAB
|
11/4/2024
|
Final Review - Corrections Needed
NEEDED:
*DRIVEWAY APPROVAL-- PENDING PAYMENT
* FLOODPLAIN ORDINANCE NOTICE TO OWNER - THIS FORM CAN BE FOUND ON THE WEBSITE UNDER THE DOCUMENTS TAB
|
11/5/2024
|
Final Review - Documents Required
NEEDED:
* FLOODPLAIN ORDINANCE NOTICE TO OWNER - THIS FORM CAN BE FOUND ON THE WEBSITE UNDER THE DOCUMENTS TAB
|
11/7/2024
|
Final Review - Documents Required
NEEDED:
* FLOODPLAIN ORDINANCE NOTICE TO OWNER - THIS FORM CAN BE FOUND ON THE WEBSITE UNDER THE DOCUMENTS TAB
|
11/20/2024
|
Final Review - Payment Needed
|
11/27/2024
|
Final Review - Payment Needed
|
12/5/2024
|
Permit Issued
Permit #000051713 created and approved.
|