| Cancelled: Building - Footer |
|
Troy Crews |
1/28/2025 |
| Cancelled: Engineering - Setbacks |
|
Troy Crews |
1/28/2025 |
| Failed: Electrical - Permanent Power |
To Complete Permit Interior Service Panel Needs To Be Inspected |
Matt Forsyth |
1/30/2025 |
| Failed: Solar - Solar Final |
To Complete This Permit Inspector Needs To See Interior Panel |
Matt Forsyth |
1/30/2025 |
| Failed: Electrical - Permanent Power |
No Access |
Gary Pitzer |
1/31/2025 |
| Failed: Solar - Solar Final |
No Access |
Gary Pitzer |
1/31/2025 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
2/4/2025 |
| Release to power company |
|
Troy Crews |
2/4/2025 |
| Passed: Solar - Solar Final |
|
Troy Crews |
2/4/2025 |
| Release to power company |
|
Troy Crews |
2/4/2025 |