Permit Details

Permit Search

Permit

Solar Power System

228 SW PILOTS WAY
LAKE CITY, FL 32024

Permit #
000051584
Application #
68082
Status Completed
  1. Submitted Nov 12, 2024
  2. Issued Nov 21, 2024
  3. Expires Aug 3, 2025
  4. Completed Feb 4, 2025

Property

Parcel #
02911-112
Owner
Sheppard Roosevelt, Sheppard Tequilla Michelle
Acres
0.50
Subdivision
May-fair Unit 1
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0290D
PV Type
Utility Interactive PV System- (DC to AC with utility connection)
Grounding
N.E.C. Chapter 690
AC Options
Exposed
AC Options (Cont..)
In Conduit
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Power Company
Clay Electric
Residential or Commercial?
Residential
Where are the panels mounted?
Roof Mounted
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Printed-Online Application
  4. Zoning Review - Reviewed
  5. Plan Review - Electrical Approved
  6. Plan Review - Building Approved
  7. Plan Review - Reviewed
  8. Final Review - Documents Required
  9. Final Review - Corrections Needed
  10. Final Review - Reviewed
  11. Final Review - Payment Needed
  12. Permit Issued

Contractors

  • Steven Robbins

    Luminate Energy Fl Llc

    License
    EC13013959
    Title
    Cert. Electrical
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Jan 28, 2025

    Cancelled: Building - Footer

    Inspected by Troy Crews

  2. Jan 28, 2025

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  3. Jan 30, 2025

    Failed: Electrical - Permanent Power

    To Complete Permit Interior Service Panel Needs To Be Inspected

    Inspected by Matt Forsyth

  4. Jan 30, 2025

    Failed: Solar - Solar Final

    To Complete This Permit Inspector Needs To See Interior Panel

    Inspected by Matt Forsyth

  5. Jan 31, 2025

    Failed: Electrical - Permanent Power

    No Access

    Inspected by Gary Pitzer

  6. Jan 31, 2025

    Failed: Solar - Solar Final

    No Access

    Inspected by Gary Pitzer

  7. Feb 4, 2025

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  8. Feb 4, 2025

    Release to power company

    Inspected by Troy Crews

  9. Feb 4, 2025

    Passed: Solar - Solar Final

    Inspected by Troy Crews

  10. Feb 4, 2025

    Release to power company

    Inspected by Troy Crews