| Inspection |
Notes |
Performed By |
Date |
| Cancelled: Engineering - Setbacks |
|
Melissa Garber |
12/3/2024 |
| Cancelled: Building - Footer |
|
Melissa Garber |
12/3/2024 |
| Passed: Building - Footer |
Bonding To Rebar Not Identified For Electrical |
Matt Forsyth |
12/3/2024 |
| Passed: Engineering - Setbacks |
Center Of Planted Pines No Identifying Markers Observed |
Matt Forsyth |
12/3/2024 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Was Under Air Pressure Water Supply Coming Through Stem Wall |
Matt Forsyth |
2/4/2025 |
| Failed: Building - Slab |
Perimeter Rebar Placement Needs To Be Chaired Up Away From Everything Minimum Three Quarters Of An Inch |
Matt Forsyth |
2/6/2025 |
| Passed: Building - Slab |
|
Matt Forsyth |
2/10/2025 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
2/28/2025 |
| Release to power company |
|
Matt Forsyth |
2/28/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Exterior Sheeting Inspected |
Matt Forsyth |
3/5/2025 |
| Passed: Electrical - Temporary Service |
Reinspection Of Temporary Service |
Matt Forsyth |
5/2/2025 |
| Release to power company |
Power Company Changed To Fpl For Re-release |
Melissa Garber |
5/12/2025 |
| Submitted Power Release through FPL Portal |
|
Garber, Melissa |
5/12/2025 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Ext Posts And Beams Approved |
Matt Forsyth |
6/4/2025 |
| Failed: Building - Framing |
Windows And Doors Need To Be Installed |
Matt Forsyth |
8/21/2025 |
| Passed: Building - Strapping |
|
Matt Forsyth |
8/21/2025 |
| Passed: Electrical - 2nd Rough-In |
Make Sure 20 Amp Receptacles Only Feed Kitchen Counter Tops |
Matt Forsyth |
8/21/2025 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
8/21/2025 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Matt Forsyth |
8/21/2025 |
| Passed: Building - Insulation |
|
Christian Allen |
10/2/2025 |