| Septic Release Inspection |
|
Health Dept |
11/14/2024 |
| Passed: Building - Footer |
|
Anthony Aslan |
11/25/2024 |
| Passed: Engineering - Setbacks |
Existing House |
Anthony Aslan |
11/25/2024 |
| Passed: Building - Slab |
Plastic Taped, Rebar And Wire In Slab, All Tie Wired |
Gary Pitzer |
12/11/2024 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
2/3/2025 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
2/3/2025 |
| Passed: Mechanical - Rough In |
|
Gary Pitzer |
4/11/2025 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
4/11/2025 |
| Passed: Building - Framing |
|
Gary Pitzer |
4/11/2025 |
| Passed: Building - Insulation |
Foam Roof, Batts In Wall Cavity |
Gary Pitzer |
4/24/2025 |
| Passed: Building - Final |
All Requirements Met For Co-- 8.15.25 Mg |
Anthony Aslan |
8/15/2025 |