| 7/15/2024 |
Application pending. |
| 7/20/2024 |
Application submitted by applicant. |
| 7/20/2024 |
City of Lake City Utilities Notified. |
| 7/23/2024 |
Point Review - Documents Required |
| 7/23/2024 |
Point Review - Printed-Online Application |
| 7/30/2024 |
Zoning Review - Reviewed |
| 7/30/2024 |
Plan Review - Documents Required |
| 8/19/2024 |
Plan Review - Documents Required |
| 8/20/2024 |
Plan Review - Documents Required |
| 8/21/2024 |
Plan Review - Documents Required |
| 9/4/2024 |
Plan Review - Documents Required |
| 9/6/2024 |
Plan Review - Documents Required |
| 9/16/2024 |
Plan Review - Plumbing Approved |
| 9/16/2024 |
Plan Review - Mechanical Approved |
| 9/16/2024 |
Plan Review - Electrical Approved |
| 9/16/2024 |
Plan Review - Building Approved |
| 9/16/2024 |
Plan Review - Reviewed |
| 9/16/2024 |
Final Review - Documents Required |
| 10/16/2024 |
Final Review - Documents Required |
| 10/24/2024 |
Final Review - Documents Required |
| 10/31/2024 |
Final Review - Documents Required |
| 11/4/2024 |
Final Review - Documents Required |
| 11/6/2024 |
Final Review - Documents Required |
| 11/7/2024 |
Final Review - Corrections Needed |
| 11/7/2024 |
Permit Issued |