10/8/2024
|
Application pending.
|
10/8/2024
|
Application submitted by applicant.
|
10/8/2024
|
City of Lake City Utilities Notified.
City of Lake City Notified of Application within Utility Service Areas LC_GAS,.
|
10/9/2024
|
Point Review - Processing
FILL IN ARCHITECT/ ENGINEER INFO
ENERGY CALCULATIONS
|
10/9/2024
|
Zoning Review - Reviewed
FILL IN ARCHITECT/ ENGINEER INFO
ENERGY CALCULATIONS
NOTICE OF COMMENCEMENT
SEPTIC APPROVAL
|
10/9/2024
|
Plan Review - Documents Required
FILL IN ARCHITECT/ ENGINEER INFO
ENERGY CALCULATIONS
NOTICE OF COMMENCEMENT
SEPTIC APPROVAL
|
10/21/2024
|
Plan Review - Documents Required
NEEDED:
*MANUAL N & ENERGY CALCULATIONS
*NOTICE OF COMMENCEMENT
*EH APPROVAL-- CONTACT 386-758-1058
*911 ADDRESS-- *PENDING DOT APPROVAL*
|
10/23/2024
|
Plan Review - Documents Required
NEEDED:
*MANUAL N & ENERGY CALCULATIONS
*NOTICE OF COMMENCEMENT
*EH APPROVAL-- CONTACT 386-758-1058
*911 ADDRESS-- *PENDING DOT APPROVAL*
|
10/25/2024
|
Plan Review - Documents Required
NEEDED:
*MANUAL N & ENERGY CALCULATIONS
*NOTICE OF COMMENCEMENT
*EH APPROVAL-- CONTACT 386-758-1058
*911 ADDRESS-- *PENDING DOT APPROVAL*
|
10/30/2024
|
Plan Review - Documents Required
NEEDED:
*NOTICE OF COMMENCEMENT
*PENDING DOT APPROVAL*
|
10/30/2024
|
Plan Review - Documents Required
NEEDED:
*NOTICE OF COMMENCEMENT
|
10/31/2024
|
Plan Review - Plumbing Approved
NEEDED:
|
10/31/2024
|
Plan Review - Mechanical Approved
NEEDED:
|
10/31/2024
|
Plan Review - Electrical Approved
NEEDED:
|
10/31/2024
|
Plan Review - Building Approved
NEEDED:
|
10/31/2024
|
Plan Review - Reviewed
NEEDED:
|
10/31/2024
|
Final Review - Processing
NEEDED:
|
10/31/2024
|
Final Review - Payment Needed
|
11/1/2024
|
Permit Issued
Permit #000051354 created and approved.
|
11/21/2024
|
Point Review - Processing
|