Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Commercial Construction Permit
Address 1992 NW BASCOM NORRIS DR
LAKE CITY, FL 32055
Parcel #: 02277-102
Acres: 70.35
Owner: New Millennium Building Systems Llc
Subdivision:
Zoning: I
Flood Zone: A
District: 3
Application #: 66704
Permit #: 000051190
Related Permit:
Submitted: Monday, August 19, 2024
Issued: Monday, October 21, 2024
Expires: Saturday, June 28, 2025
Completed:
Status: Permit Issued
Septic Release? No
Notes:

LAKE CITY UTLITY CUSTOMER SERVICE NOTES The City of Lake City provides water, sewer and natural gas to this location. Locates must be obtained to ensure that the existing utility infrastructure is not damaged or obstructed.
Job Details
This is the construction of a: Guard House
Describe commercial use: Guard House
Heated Area (Sqft) 420
Total Area (Sqft) 420
Stories 1
Building Height 15
Driveway access to property: Existing Drive
Is there a Fire Sprinkler System? No
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Business
Dev Permit # F023-
Service Amps 200
Building Code Edition 2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Elevation regulation Minimum Requirement
Finished floor requirement One foot above the road
Fema map number 12023C0283D
Sealed roof decking options. (Must select one.) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Review Notes
8/19/2024 Application pending.
8/19/2024 Application submitted by applicant.
8/19/2024 City of Lake City Utilities Notified. City of Lake City Notified of Application within Utility Service Areas LC_GAS, LC_WATER, LC_SEWER.
8/26/2024 Point Review - On Hold-Incomplete NEEDED * MISSING S.1-3 * AUTH FOR ADAM STROSSER TO SIGN AS OWNER * ENVIRONMENTAL HEALTH SIGNED SITE PLAN OR CITY AVAILIBILITY LETTER ****UPON PLAN REVIEW ADDITIONAL DOCUMENTS MAYBE REQUIRED: MANUAL J, ENERGY CALCS, COMMERCIAL CHECKLIST AND MORE
9/11/2024 Point Review - Processing NEEDED
9/11/2024 Zoning Review - Reviewed NEEDED
9/11/2024 Plan Review - Reviewed NEEDED
9/11/2024 Final Review - Processing NEEDED
9/11/2024 Final Review - Reviewed NEEDED
9/11/2024 Final Review - Payment Needed NEEDED
9/20/2024 Final Review - Payment Needed
10/2/2024 Final Review - Payment Needed
10/9/2024 Final Review - Payment Needed
10/21/2024 Final Review - Payment Needed
10/21/2024 Permit Issued Permit #000051190 created and approved.
Contractors
Name/ Business License Title Role
Kevin L Bedenbaugh Jr
Plumb Level Construction Co Llc
CGC1516042 General Contractor Contractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Ryan Felknor
Felknor Electric, Inc.
Workers Comp & Employees Workers Comp Expired.
EC13003153 Electrical Contractor Subcontractor
Clinton G Wilson
Wilson Heat & Air Inc
CAC057886 Class B A/c Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 10/25/2024
Passed: Building - Monolithic Slab Troy Crews 10/30/2024
Passed: Engineering - Setbacks Troy Crews 10/30/2024
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 11/20/2024
Passed: Building - Framing Troy Crews 11/20/2024
Passed: Building - Roof Decking Troy Crews 11/20/2024
Passed: Electrical - 2nd Rough-In Troy Crews 11/20/2024
Passed: Mechanical - Rough In Troy Crews 11/20/2024
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 11/20/2024
Passed: Building - Insulation All Spray Foam Troy Crews 12/30/2024
Failed: Building - Final Gfci Plugs Exterior Not Tripping Open Wiring Out Of Wall Restroom. Troy Crews 2/4/2025