Permit Details

Permit Search

Permit

New Residential Construction

1965 SW COUNTY ROAD 18
FORT WHITE, FL 32038

Permit #
000050811
Application #
66621
Status Completed
  1. Submitted Aug 15, 2024
  2. Issued Sep 13, 2024
  3. Expires Sep 24, 2025
  4. Completed Mar 28, 2025

Property

Parcel #
09807-002
Owner
Reyna Nancy N, Poole Jocelyn
Acres
9.35
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0495C
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
1960
Total Area (Sqft)
3546
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
SINGLE FAMILY DWELLING
Building Code Edition
2023 Florida Building Code 8th Edition and 2020 National Electrical Code
Septic# (00-0000) or (X00-000)
24-0615
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Service Amps
200

Status & Review History

  1. Point Review - Printed-Online Application
  2. Zoning Review - Reviewed
  3. Plan Review - Corrections Needed
  4. Plan Review - Corrections Needed
  5. Plan Review - Corrections Needed
  6. Plan Review - Building Approved
  7. Plan Review - Electrical Approved
  8. Plan Review - Mechanical Approved
  9. Plan Review - Plumbing Approved
  10. Plan Review - Fuel/Gas Approved
  11. Plan Review - Reviewed
  12. Final Review - Reviewed
  13. Final Review - Payment Needed
  14. Permit Issued
  15. Final Review - Payment Needed

Contractors

  • Brian T Giebeig

    Trent Giebeig Construction,inc.

    License
    CRC1330693
    Title
    Residential Contractor
    Role
    Contractor
  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Derrick L Williams

    D L Williams Heating & Cooling Llc

    License
    CAC1816913
    Title
    Class "b" A/c Contractor
    Role
    Subcontractor
  • Kenneth R Roche

    Ken Roche Plumbing Inc Dba Plumbing Now

    License
    CFC1426527
    Title
    Plumbing Contractor
    Role
    Subcontractor

Inspections

  1. Sep 18, 2024

    Passed: Building - Footer

    Need Picture Of Grounding Wire

    Inspected by Anthony Aslan

  2. Sep 18, 2024

    Passed: Engineering - Setbacks

    Appears To Be With In Setbacks

    Inspected by Anthony Aslan

  3. Sep 25, 2024

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  4. Oct 4, 2024

    Passed: Building - Slab

    Inspected by Anthony Aslan

  5. Oct 24, 2024

    Passed: Building - Wall Sheathing

    Inspected by Anthony Aslan

  6. Oct 24, 2024

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  7. Oct 30, 2024

    Passed: Building - Framing

    Inspected by Anthony Aslan

  8. Oct 30, 2024

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  9. Oct 30, 2024

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  10. Oct 30, 2024

    Release to power company

    Inspected by Anthony Aslan

  11. Nov 21, 2024

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Anthony Aslan

  12. Nov 21, 2024

    Failed: Mechanical - Rough In

    Exhaust Venting Not Strapped And Not Allowed Over Windows fire Place Vent Piping Not Rated For Concealment In Attic

    Inspected by Anthony Aslan

  13. Nov 26, 2024

    Passed: Mechanical - Rough In

    Corrections Made

    Inspected by Anthony Aslan

  14. Nov 26, 2024

    Passed: Building - Insulation

    Walls Only

    Inspected by Anthony Aslan

  15. Jan 15, 2025

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Anthony Aslan

  16. Jan 17, 2025

    Release to power company

    Septic Rec'd

    Inspected by Melissa Garber

  17. Jan 17, 2025

    Septic Release Inspection

    Inspected by Health Dept

  18. Mar 28, 2025

    Passed: Building - Final

    **backflow Preventers On Hose Bibs **blower Door And Termite Final Required Prior To Co-- 3.28.25

    Inspected by Anthony Aslan

Documents